Tiruchirappalli City Municipal Corporation has accelerated work on its underground drainage (UGD) expansion, with Phase IV covering previously unserved areas of the city crossing 40% completion in pipeline installation. As of October, 60.3 km of the planned 143.65-km sewer network had been laid, while 7,305 of the proposed 16,500 underground sewer connections had been provided. The wider UGD programme covers multiple phases and revamping works across the city, with the projects aimed at extending sewerage infrastructure to areas that were left out of earlier phases and connecting the network to sewage treatment infrastructure at Panjapur.
Phase IV is being implemented in the uncovered portions of eight wards, including areas along Kuzhumani Road, Vayalur Road, Karumandapam, Ponmalaipatti, KK Nagar and K Sathanur. The project involves 143.65 km of sewage collection pipelines, 35.08 km of pumping lines, 5,872 manholes and 16,500 household sewer connections. According to the progress reported in October, 8.3 km of the pumping network had been completed and 2,856 manholes had been constructed. Seven of the nine pumping stations and 16 of the 17 lifting stations were also under construction. The project has a revised estimated cost of INR 230.61 crore under the AMRUT 2.0 framework.
The Phase IV works were awarded in October 2024 to a joint venture of N.S. Patel & Co., SVD Infracon and SKP Constructions. The work order was valued at INR 235.06 crore, including five years of operation and maintenance. The project is intended to extend sewerage infrastructure to locations including Linga Nagar, Uyyakondan Thirumalai, Pirattiyur, Olaiyur and Pasumai Nagar, covering wards 8, 25, 46, 55, 56, 63, 64 and 65. The Ministry of Housing and Urban Affairs' AMRUT 2.0 platform separately lists the Phase IV UGD project for the left-out areas of Tiruchirappalli Corporation as a contract-awarded sewerage project.
The expansion is being carried out alongside progress in other components of Tiruchi's UGD programme. Phase II, implemented at a cost of INR 377.29 crore, has been completed, while Phase III, estimated at INR 425.72 crore, is nearing completion after almost the entire planned sewer pipeline and pumping network was laid. Revamping works under the Smart Cities Mission, covering 30 wards at a cost of INR 210 crore, are also nearing completion. Together, these projects are intended to extend the city's sewerage network and increase the number of properties connected to underground drainage infrastructure.
A 100 MLD sewage treatment plant at Panjapur is another key component of the programme. The plant, estimated at about INR 233.87 crore in the Corporation's reported project details, was around 88% complete in October, with commissioning targeted by the end of 2026. The Phase IV network is planned to connect to this treatment facility. At the same time, residents have raised concerns about roads affected by UGD construction, particularly ahead of the northeast monsoon. More than 750 km of roads across the city have reportedly been disturbed during implementation of the earlier UGD phases, making road restoration an important parallel requirement as the sewerage expansion progresses.