The Uttar Pradesh cabinet has approved the Lucknow Development Authority’s proposal to release 2,747 plots in Sushant Golf City that Ansal Properties and Infrastructure Ltd had sold despite the plots being mortgaged to the authority. The registries of these plots will not be cancelled. LDA will complete pending development work in the township and release the mortgaged plots in phases after issuing completion certificates. The authority will also approach the National Company Law Tribunal for the project’s takeover and completion. The move is part of a wider plan aimed at addressing the long-pending issues faced by thousands of homebuyers and plot owners.
The Uttar Pradesh cabinet has cleared the Lucknow Development Authority’s proposal to release 2,747 mortgaged plots in Sushant Golf City, Lucknow, which were sold by Ansal Properties and Infrastructure Ltd without the authority’s permission. LDA vice-chairperson Prathamesh Kumar said the registries of these plots would not be cancelled, avoiding further uncertainty for the buyers.
The cabinet approval was granted at a meeting held last week. Following the decision, the LDA will place its proposal before the National Company Law Tribunal (NCLT), where the insolvency proceedings related to the township are underway. Further action on the takeover and completion of the project will follow the required permissions.
According to the LDA, Ansal had mortgaged 3,489 plots with the authority as security under the township agreement. The mortgage was intended to protect the authority in case the developer failed to complete the promised development work. Under the applicable conditions, these mortgaged plots could not be sold by the developer without prior permission from the LDA. However, 2,747 of these plots were subsequently sold and registered in buyers’ names.
The authority had earlier considered cancelling the registrations of the 2,747 plots. However, LDA officials said such a step could have left genuine buyers in uncertainty despite having purchased the properties. The revised approach is therefore to release the mortgaged plots while also completing the pending development works in the township.
The release of the plots will take place sector-wise or pocket-wise. LDA will first undertake development work in the partially developed and undeveloped areas and issue completion certificates for the respective sectors or pockets. Once the required work is completed, the mortgaged plots will be released proportionately.
There is also a provision for plot owners who want their mortgaged plots released before completion of the development work. Such owners will have to deposit a guarantee with the LDA equivalent to the fee fixed by the authority’s board. The guarantee will be returned after the required development work is completed and the completion certificate is issued.
The decision is part of a larger plan for the LDA to take over and complete the stalled township. The project is expected to affect around 5,000 homebuyers, including people awaiting possession of houses or plots. The proposed takeover still requires the NCLT process to be completed because the developer is undergoing insolvency proceedings.
The scale of the pending work remains substantial. Around 50 kilometres of roads are yet to be completed, while the township also requires 440 KVA and 220 KVA power substations. Other unfinished works include tube wells, water pipelines, sewer lines, parks and drainage infrastructure.
The tentative cost of completing the outstanding development work has been estimated at INR 2,216.91 crore. This includes about INR 453.10 crore for infrastructure work in pockets 1 to 4, INR 1,126.52 crore for pocket 5, INR 114.28 crore for the remaining work on a railway overbridge and around INR 523 crore for substations. The final liability, however, will be determined through the insolvency resolution process by the interim resolution professional.
The preliminary maximum liability associated with the takeover has been estimated at around INR 2,912 crore. The state government is expected to provide the funds required to meet liabilities finalised through the resolution process as seed capital for the LDA.
The authority is also facing a funding challenge because a substantial portion of the land that had been mortgaged as security has already been sold. LDA officials have said that around 70% of the mortgaged land, covering about 411 acres, had been sold by the developer. This has reduced the authority’s ability to use the mortgaged land to generate funds for completing the township.
In view of this funding gap, the LDA has been considering a completion charge for some existing property owners. The proposed charge could apply to middle-income group and higher-income group property owners when they approach the authority for approval of building plans. Buyers in the lower-income group and economically weaker section categories would remain exempt under the proposal. The amount of the proposed charge has not yet been finalised.
The LDA has also drawn up a phased approach for the township based on the extent of development in different areas. Developed portions are to be taken forward for completion and handover, while partially developed areas require infrastructure and power-related work. Issues involving undeveloped land and pending land-related matters will also have to be addressed as the authority moves ahead with the takeover.
The wider land issue extends beyond the mortgaged plots. LDA officials have also raised concerns regarding land belonging to village communities and the municipal corporation, as well as land associated with a consortium. A recent report said around 164 hectares of such land had been sold, adding another layer to the documentation and legal process surrounding the township.
Earlier reports had also indicated that several mortgaged plots already had construction on them. Around 440 plots were reported to have completed houses or bungalows, while 81 had partial construction. This has added to the importance of resolving the status of the registrations without leaving existing owners in prolonged uncertainty.
The LDA will now have to work through the documentation, claims, liabilities and legal proceedings before the township can move towards full completion. The authority has indicated that claims approved through the NCLT process will be considered while determining