The Prayagraj Development Authority has sent the revised detailed project report (DPR) for the Prayagraj Metro to the Uttar Pradesh Metro Rail Corporation (UPMRC) for approval, reports said on 11 November. The project, estimated at about INR 12,000 crore, has two corridors, one from Shantipuram to Chheoki and the other from Jhunsi to the airport and Aerocity, meeting at Parade. The plan replaces the earlier Metrolite proposal with a full metro. It needs approval from the state government and then the Centre. A ropeway is also to be linked at Parade. Headline figures differ, and the cost is yet to be confirmed.
The Prayagraj Development Authority (PDA) has sent the detailed project report (DPR) for the proposed Prayagraj Metro to the Uttar Pradesh Metro Rail Corporation (UPMRC) for approval, according to reports of 11 November. The project is estimated to cost about INR 12,000 crore.
The proposed metro would run on two corridors. The first runs from Shantipuram in Phaphamau to Chheoki in Naini. The second runs from Jhunsi to the airport and the planned Aerocity area, via Bamrauli. The two corridors are to meet at Parade, which is proposed as the junction and interchange hub. The PDA’s vice-chairman, Rishi Raj, said the updated DPR includes the extension of the Jhunsi-Bamrauli corridor to the airport. A planned Parade ropeway station is intended to be integrated with the metro interchange so passengers can move between the metro and the ropeway.
RITES, a Ministry of Railways undertaking, prepared the revised report after UPMRC asked for a fresh assessment of a full-fledged metro system, and carried out a new survey last year. The revised DPR was submitted to UPMRC in October. The project needs approval from the state government first. UPMRC then forwards it to the Centre, which must also approve it. The reports do not say when the state decision is expected.
The proposal has grown a lot. The earlier Metrolite plan, which the state approved in 2021, was estimated at INR 8,747 crore. In October 2025 the state moved to replace it with a conventional metro of 44 km with 39 stations across two corridors, at about INR 10,000 crore. Corridor I was to run 23 km from Bamrauli to Jhunsi and Corridor II 21 km from Shantipuram to Chheoki. Later reports said the revised plan would stretch to nearly 60 km with about 45 stations, adding the airport and a Sangam link, at a cost of more than INR 12,000 crore. In July, the PDA decided to fold the ropeway proposal into the same DPR and told RITES to revise the report, with an updated version due by 15 August.
Prayagraj is one of several UP cities with proposed metro systems, and UPMRC is working as interim consultant for the project. Reports note that other clearances will also be needed, including defence land clearance, but none of these has been confirmed for the revised plan.
The reports I found do not give a final route length, the number of stations or the funding pattern. Some summaries are based on earlier versions of the plan, so these details should be checked with the DPR.
Source: Prayagraj Development Authority