SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Chennai building approvals delayed by portal glitches and pending rule updates

#Infrastructure News#Infrastructure#India#Tamil Nadu#Chennai
Synopsis

Building approval processes in Chennai are facing delays as local bodies have yet to incorporate Tamil Nadu government's recent regulatory relaxations into the single-window planning permission portal, while technical problems continue to affect the Chennai Metropolitan Development Authority's (CMDA) online system. The issues have left more than 1,000 building proposals awaiting clearance, according to industry representatives. The government had introduced Government Orders (GOs) 179, 180 and 194 to enable third-party certification, delegate approval powers to local authorities and revise building height and development regulations. However, developers remain unable to access several of these provisions through the online system. The delays have also affected application submissions, statutory clearances, payments and completion certificate processing, prompting industry bodies to seek intervention from the authorities.

Building approvals in Chennai are facing delays because local bodies have not updated the single-window planning permission portal to incorporate Tamil Nadu government's latest regulatory relaxations, while recurring technical glitches in the Chennai Metropolitan Development Authority's (CMDA) existing system are disrupting applications, developers said on Thursday. The problems have left more than 1,000 proposals awaiting processing and are affecting project schedules, financing costs and new launches. 
The state government issued GOs 179, 180 and 194 nearly a month ago, introducing third-party certification, expanding the approval powers of local bodies and revising permissible building heights and other development norms. However, the revised provisions have not yet been integrated into the online planning permission system, preventing applicants from using the changes while submitting proposals. 
Under GO 179, registered architects and Grade-I engineers are permitted to certify specified residential, commercial and industrial buildings. GO 180 delegates approval powers to local bodies for residential projects with a floor space index (FSI) of up to 1,500 sq m and commercial buildings with an FSI of up to 500 sq m. GO 194 increases the permissible building height from 18.3 metres to 19.5 metres and revises provisions relating to road width, setbacks and parking. 
S Ramaprabhu of the Builders' Association of India said more than 1,000 proposals were in limbo because applicants could neither submit plans under the revised provisions nor access the intended relaxations. He said the portal software should have been updated before the new provisions were rolled out. Greater Chennai Corporation commissioner G S Sameeran said the required update would be carried out soon. 
Separately, developers have reported repeated problems with CMDA's existing online approval system. In a representation submitted to CMDA on October 26, CREDAI Chennai listed difficulties in submitting applications, uploading documents and revised drawings, obtaining statutory no-objection certificates, paying charges and tracking application status. The representation also highlighted delays in acknowledgements for completion certificates and difficulties accessing essential services. 
A developer cited in the report said the glitches were recurring and affected almost every stage of the process, from initial submission and scrutiny to fee payment, receipt generation, digital signatures and the issue of planning permission. Completion certificate applications and their subsequent approvals were also affected. 
The problems were said to extend beyond the planning approval portal. Developers seeking water and sewerage connections from the Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB), even after receiving completion certificates, were reportedly being told that infrastructure development charges payable by CMDA had not been transferred. The developer called for government intervention to ensure applicants were not charged interest or penalties when delays resulted solely from technical failures in the portal or related systems. 
A senior CMDA official said a special team led by the chief planner and the senior planner for e-governance had been formed to address the technical issues. The authority was also floating a tender for a new artificial intelligence-based online planning permission application system