SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Thiruvananthapuram civic body targets December restart for stalled INR 157.5 crore sewerage project

#Infrastructure News#Infrastructure#India#Kerala#Thiruvananthapuram
Synopsis

The Thiruvananthapuram Corporation is aiming to restart its stalled INR 157.5 crore sewerage project covering Attukal, Kalady and Ambalathara in the first week of December 2026. The civic body has approved a proposal to use funds from the 16th Finance Commission to address the funding constraints that halted construction. The proposal will be placed before the district planning committee for consideration. The project was disrupted after a INR 66.63 crore National Housing Bank loan lapsed, affecting contractor payments and progress on the pipeline network.

The Thiruvananthapuram Corporation is targeting the first week of December 2026 to resume construction of its stalled INR 157.5 crore sewerage project covering Attukal, Kalady and Ambalathara. The proposed restart follows the civic body's decision to use funds from the 16th Finance Commission to address the financial constraints that brought work to a halt. 
According to reports by The Times of India and Urban Acres, the corporation council has approved the funding proposal, which is scheduled to be placed before the district planning committee for consideration on November 9. Corporation secretary Muhammad Shafi said pending bills connected with the project would be cleared, including INR 6 lakh required to obtain road-cutting permission from the Public Works Department (PWD). 
The corporation expects the existing contractor to resume construction once the funding process is completed. Officials have indicated that a fresh tender will not be necessary, potentially allowing work to restart without the additional time required for a new procurement process. The proposed arrangement is intended to resolve the immediate payment and permission-related issues that have prevented construction from progressing. 
The project was stalled after a INR 66.63 crore loan secured from the National Housing Bank (NHB) lapsed in February 2026. The loan had been obtained in September 2024, but expired after the required progress report was not communicated to the bank. The corporation reportedly became aware of the lapse only in July. The funding disruption subsequently affected payments to the contractor and delayed construction. 
The project had been planned in two packages covering the Attukal-Kalady and Attukal-Ambalathara areas. The original estimates placed the packages at approximately INR 66.5 crore and INR 91 crore, respectively. Together, the works envisage a sewer network extending around 44.7 km and 4,338 connections. The project is intended to expand sewerage infrastructure in the three localities, where pipeline installation requires excavation along existing roads. 
Before the stoppage, the contractor had mobilised labour and machinery and completed approximately 1 km of pipeline work. The delay also left excavated sections of roads awaiting further construction and restoration. In September, the corporation had asked the Kerala Water Authority (KWA) to fill trenches dug for pipeline installation. The pending INR 6 lakh deposit for road-cutting permission had also prevented the authority from providing additional work fronts. 
The proposed December restart is particularly significant for Attukal ahead of the 2027 Attukal Pongala festival, which draws lakhs of devotees to the area. Completion of sewerage work and restoration of affected roads will be important for maintaining access and traffic movement during the annual event. The corporation's immediate priorities are to secure approval for the proposed funding arrangement, clear outstanding payments and obtain the necessary road-cutting permission before the contractor resumes work.