Singapore will build five new gas-fired power plants to raise its electricity generation capacity by around 26% from about 12 gigawatts in the early 2030s, Minister for Energy, Trade and Industry Tan See Leng said on Monday. The projects form part of the Energy Market Authority's five-year plan to meet rising demand from semiconductor manufacturing, data centres and electric vehicles. The city state also plans up to SGD 5.3 billion of grid investment, a second LNG terminal and a second interconnector with Peninsular Malaysia.
Singapore will add five new gas-fired power plants to increase its electricity generation capacity by around 26% early in the next decade, up from roughly 12 gigawatts at present, Tan See Leng, Minister for Energy, Trade and Industry, said on Monday. Speaking at the Singapore International Energy Week conference, Tan said the projects form part of the Energy Market Authority's five-year plan to meet growth in demand and improve the city state's energy resilience.
The Energy Market Authority (EMA) is currently evaluating proposals for the additional gas-fired projects, which are due to be operational by 2032. The regulator will launch further requests for proposals over the next five years if demand growth stays strong. Peak electricity demand stood at 8.6 GW as of August 2026 and could reach between 9.9 GW and 13 GW by 2031, driven by semiconductor manufacturing, data centres and electric vehicles.
Natural gas currently supplies about 95% of the city state's electricity, and Singapore is expanding its capacity to import the fuel. Liquefied natural gas regasification capacity will rise to 15 million tonnes per annum from 10 million tonnes per annum once a second terminal at Jurong Port begins operating by 2030, adding import capacity for the fuel that underpins most of Singapore's power generation.
Singapore expects to invest up to SGD 5.3 billion, or about USD 4.15 billion, in its power grid between 2025 and 2029. The programme includes seven new transmission substations by 2031, compared with four built in the previous five years. Marine subsea surveys also began this month for a second interconnector with Peninsular Malaysia, which would add up to 2 GW of capacity by 2030 alongside the existing 1 GW link between the two countries.
Energy storage capacity is set to rise to just over 1 gigawatt-hour by 2030 from about 350 megawatt-hours at present. Solar capacity currently stands at 2.3 gigawatt-peak, and Singapore is targeting 3 GWp of solar capacity by 2030 and 4 GWp by 2035, according to the details outlined alongside the minister's announcement at the Singapore International Energy Week conference on Monday.
Source- Reuters