The Greater Chennai Corporation is progressing with an INR 80.25 crore stormwater drain project in Korattur to reduce recurring monsoon flooding in residential areas, including Central Avenue, East Avenue and the Tamil Nadu Housing Board Colony. The nearly 5-km drainage network is being developed in two phases, with the first covering 2.44 km and the second extending approximately 2.5 km towards the Cooum River. Officials said 1.8 km of the first phase had been completed, while discussions on the second phase were under way. The project is intended to improve rainwater discharge and ease pressure on existing drainage channels.
The Greater Chennai Corporation (GCC) is implementing a stormwater drainage project worth INR 80.25 crore in Korattur, aiming to address recurring waterlogging during the monsoon season. The nearly 5-km network is intended to improve rainwater movement from flood-prone neighbourhoods towards the Cooum River and reduce pressure on existing drainage channels.
The project is being executed in two phases. The first phase covers 2.44 km at an estimated cost of INR 40.36 crore. According to information reported by Urban Acres, approximately 1.8 km of this section had been completed. The second phase will cover around 2.5 km and has an estimated cost of INR 39.89 crore. A stakeholders' meeting has been held to discuss the next stage of implementation.
The proposed drainage route begins near Kiran Palace, close to Central Avenue, and runs along GNT Road towards the Cooum. The completed network is expected to divert runoff from vulnerable parts of Korattur and provide an additional channel for managing excess water during periods of heavy rainfall.
Areas expected to benefit include Central Avenue, East Avenue and the Tamil Nadu Housing Board (TNHB) Colony, where residents have experienced recurring flooding during the monsoon. Waterlogging in these neighbourhoods can disrupt road traffic, affect access to homes and interfere with daily activities. The new drainage system is intended to improve the movement of stormwater away from these residential areas.
The design of the second phase was finalised following a joint survey involving Chennai Metro Rail Limited and the Chennai Metropolitan Water Supply and Sewerage Board. The assessment examined water inflows from North Avenue and the surrounding catchment, as well as the levels required to connect the proposed drain to the Cooum River. These considerations are important to ensure that the drainage network can carry runoff towards its intended outlet.
The project is also expected to act as a relief channel for Otteri Nullah during heavy rainfall. However, residents have raised concerns about whether diverting additional water could increase pressure on the waterway or affect communities along its course. Sandhya Vedullapalli, secretary of the Federation of Anna Nagar Residents Association, has called for flood mitigation measures that also protect water quality and the ecological health of nearby areas.
The project’s effectiveness will depend on the completion of both phases and the ability of the connected drainage system to carry water through to the intended outlet. The corporation has not provided a confirmed completion date in the available reports.
The Korattur project forms part of Chennai's wider efforts to improve stormwater management and reduce monsoon-related disruption. Its long-term performance will depend on construction progress, coordination between agencies and the capacity of downstream waterways to accommodate the additional flow.