The Maharashtra government has approved the diversion of 4.985 hectares of forest land for the proposed goods siding yard at Boisar railway station in Palghar district. The project, being developed by Mumbai Rail Vikas Corporation under MUTP-III, is linked to the proposed quadrupling of the Virar-Dahanu railway section. The relocation of the existing western goods yard is planned to clear the alignment for additional tracks. The approval also provides for compensatory afforestation on degraded forest land in Boisar.
The Maharashtra government has approved the diversion of 4.985 hectares of forest land for the proposed goods siding yard at Boisar railway station in Palghar district, clearing a key administrative hurdle for the relocation of the existing western goods yard. The project is being implemented by Mumbai Rail Vikas Corporation (MRVC) under the Mumbai Urban Transport Project-III (MUTP-III).
The approved forest area covers 4.1855 hectares for the goods siding yard and 0.7995 hectares for an approach road. The project will also require 7.7721 hectares of non-forest land, taking the total land requirement to about 12.76 hectares. The Union Ministry of Environment, Forest and Climate Change (MoEFCC) had earlier granted approval for diversion of the forest land.
According to documents reviewed by the Forest Advisory Committee, the proposed site is not within 10 km of a wildlife sanctuary, national park, tiger reserve or tiger corridor. The state government has also reported that the project will not require displacement of human habitation. For compensatory afforestation, about 12.918 hectares of degraded forest land has been identified in Reserve Forest Compartment No. 84 in Boisar, Palghar taluka. The forest department has certified the land as suitable for afforestation and management and free from encroachment.
The relocation is linked to the proposed quadrupling of the Western Railway line between Virar and Dahanu. Boisar currently has two goods-handling yards outside the railway station. The yard near the station handles freight traffic serving industrial units in the surrounding area, with around 80-100 trailers moving daily, while another yard beyond the Khairapada bridge handles heavy goods, including steel billets manufactured in Boisar and Tarapur.
The western goods yard is situated along the alignment required for the proposed railway expansion. Its relocation has therefore been planned to create the space needed for additional railway tracks. The new site is proposed near the old BARC warehouse adjoining the Chitralaya area in Boisar West and comprises a combination of private and protected forest land.
The forest diversion order enables MRVC to move ahead with the land-related component of the new siding yard. The shift is expected to support the broader railway expansion programme by removing the existing goods yard from the alignment of the proposed additional tracks.
The Boisar project forms part of MUTP-III, which includes several capacity-enhancement works on Mumbai’s suburban rail network and the wider northern corridor. The quadrupling of the Dahanu-Virar section is also being planned in the context of rising passenger and freight requirements in the extended Mumbai Metropolitan Region, including industrial activity in Palghar and future infrastructure development around Vadhavan Port.
The latest approval does not itself mark completion of the new yard. Construction and subsequent operationalisation will depend on further project execution and compliance with applicable forest and infrastructure-related conditions. However, the diversion of the required forest parcel removes a significant land-related constraint to relocating the goods facility and progressing the planned railway expansion at Boisar.