SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

MMRDA begins elevated Eastern Freeway construction over live traffic

#Infrastructure News#Infrastructure#India#Maharashtra#Mumbai City
Synopsis

The Mumbai Metropolitan Region Development Authority (MMRDA) has started erecting precast segments for the 13.9-km, six-lane Elevated Eastern Freeway Extension (EFE), marking the shift from foundation and pier works to construction of the elevated corridor’s main structure. The first segment, weighing more than 90 tonnes, was launched near Bhandup Pumping Station using a 115-metre-long mechanised launching gantry. The project will use 1,632 precast segments to form 288 full spans. Once completed, the corridor will connect Anand Nagar in Thane with Chheda Nagar in Ghatkopar and is expected to improve travel between Thane and South Mumbai.

The Mumbai Metropolitan Region Development Authority (MMRDA) has started erecting precast segments for the 13.9-km, six-lane Elevated Eastern Freeway Extension (EFE), with construction now moving from foundation and substructure works to the elevated corridor’s superstructure. 
The first precast segment, weighing more than 90 tonnes, was erected at Pier P78 near Bhandup Pumping Station using a 115-metre-long mechanised Launching Gantry-01 (LG-01). The work was carried out above the Eastern Express Highway while traffic continued to move below. 
The launch marks an important stage in the construction of the corridor, as the project moves into the process of joining the precast segments to create complete elevated bridge spans. 
The mechanised launching gantry has been designed to lift, position and erect the heavy precast segments with limited support from the ground. This allows construction to continue over an operational traffic corridor while reducing interference with vehicles using the Eastern Express Highway. The gantry also underwent third-party testing before being deployed for the first segment. 
LG-01 will progressively erect 1,632 precast segments in the direction of Mumbai. These segments will be longitudinally post-tensioned to form the complete bridge spans. 
A second launching gantry, LG-02, will advance from Vikhroli towards Mumbai. At the same time, the Ground Support System (GSS) will progress between Bhandup and Kanjurmarg towards Thane. 
The project is designed around 288 full spans, with each typical span measuring around 40 metres and comprising 16 precast segments. The maximum weight of an individual segment is 106 tonnes, while a complete span can weigh up to 1,450 tonnes. The typical structure has a top width of 25 metres and a bottom width of seven metres. 
Construction has also progressed across the project's foundations and supporting structures. Around 81% of the monopiles and 19% of the group piles have been completed, while 51% of the piers and 33% of the pier caps are complete. So far, 135 of the planned 3,732 precast segments have been cast. 
The EFE uses 2,500-mm-diameter monopiles and a single-pier arrangement that removes the need for conventional pile caps. Along with the mechanised launching system, this approach is intended to reduce the construction footprint and allow work to continue above a busy operational road. 
The corridor will connect Anand Nagar in Thane with Chheda Nagar in Ghatkopar. It is being developed to provide an alternative high-capacity route and reduce pressure on the Eastern Express Highway, which carries heavy traffic between Mumbai and the Thane side of the Mumbai Metropolitan Region. 
Once operational, the elevated corridor is expected to bring the travel time between South Mumbai and Thane down to around 20–25 minutes. It is also expected to improve connectivity between eastern Mumbai, Thane and other parts of the metropolitan region. 
The start of span erection gives the Elevated Eastern Freeway Extension a visible presence above the Eastern Express Highway, but a large part of the construction work remains ahead. With thousands of precast segments to be cast and installed, the project will now depend on the coordinated progress of its launching gantries, foundations, piers and span assembly. The use of mechanised construction is particularly relevant for this corridor because much of the work is taking place alongside or above existing traffic. Its eventual impact will depend on how smoothly the completed route integrates with the surrounding road network. 
Source MMRDA