Mangaluru City Corporation Commissioner Rahul Ratnam Pandey has reviewed the proposed multi-level car parking (MLCP) facility at the old bus stand on KS Rao Road and directed officials to submit a month-wise milestone plan covering the next 15 months. The project is being pursued under a public-private partnership model but faces land-related hurdles, with around 84 landowners in and around the project area and some unwilling to part with land required for access and roads. During the same inspection, Pandey visited a proposed wet-well site at Surathkal-Idya after residents raised concerns that the facility could contaminate local well water. He directed officials to collect water samples and have them tested in a laboratory.
Mangaluru City Corporation (MCC) Commissioner Rahul Ratnam Pandey has sought a structured implementation schedule for the proposed multi-level car parking facility at the old bus stand premises on KS Rao Road, directing officials to submit a month-wise milestone report covering 15 months within a week.
The proposed MLCP project is being developed under a public-private partnership (PPP) model. During his inspection, Mangaluru Smart City Limited General Manager Arun Prabha briefed the commissioner on the bidding process, proposed investment, construction quality requirements and land-related issues.
Land acquisition has emerged as one of the key challenges for the project. Officials said around 84 landowners are associated with properties in and around the project area, with some owners unwilling to part with land needed for roads and other project requirements. A proposal is also under consideration to lease the project land to the successful bidder for 30 years.
The site includes the old bus stand building, which officials said is more than seven decades old. Several buildings in the surrounding area are around 40 years old. The commissioner’s review therefore covered not only the proposed parking facility but also the land and construction-related requirements that need to be resolved for the project to progress.
The month-wise milestone schedule is intended to provide a framework for monitoring the project over the next 15 months. Officials have been asked to submit the plan within seven days, allowing the civic administration to track progress against specific stages of implementation.
Pandey subsequently inspected the wet-well site at Surathkal-Idya, where residents raised objections to the proposed installation. Residents alleged that the system could be responsible for contamination of well water in the locality.
The commissioner inspected the well water at the site and directed officials to collect samples and send them to a laboratory for quality testing. The testing is expected to provide an assessment of the water quality amid the concerns raised by residents.
Pandey told residents that their concerns would be considered and that the matter would be examined comprehensively. He also indicated that no action would be taken against their wishes while the concerns were being assessed. Officials from the MCC engineering department and the Karnataka Urban Infrastructure Development and Finance Corporation were present during the inspection.
The two inspections covered separate infrastructure issues — implementation and land constraints affecting the central-city parking project, and environmental and community concerns surrounding the proposed wet-well facility at Surathkal-Idya.