SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

National Grid's North Humber to High Marnham electricity link advances after planning application acceptance

#International News#Industrial#United Kingdom
Synopsis

National Grid's application for its proposed North Humber to High Marnham electricity transmission link has been accepted by the Planning Inspectorate, marking a key milestone in the project's planning process. The development includes around 90 kilometres of new 400kV overhead electricity lines intended to strengthen transmission capacity between the Humber region and the East Midlands. The project forms part of The Great Grid Upgrade and could also establish an £18 million community fund if development consent is granted.

National Grid’s application for its proposed North Humber to High Marnham electricity transmission link has been accepted by the Planning Inspectorate, allowing the project to move into the pre-examination stage of the UK’s nationally significant infrastructure planning process. 
The project is intended to reinforce electricity transmission capacity between the Humber region and the East Midlands, enabling more power to be transported across the network. National Grid’s proposals include around 90 kilometres of new 400-kilovolt (kV) overhead line, with sections of the route running close to existing overhead lines. The route crosses the East Riding of Yorkshire, North Lincolnshire and Bassetlaw District in Nottinghamshire. 
The link forms part of The Great Grid Upgrade, National Grid’s programme to modernise and expand the electricity transmission network. The wider programme is intended to increase the system’s capacity to accommodate rising electricity demand and growing volumes of domestically generated power, including offshore wind produced along the east coast of England. 
National Grid submitted its Development Consent Order (DCO) application to the Planning Inspectorate on 16 October 2026. The application’s acceptance follows the regulator’s review of whether the submission meets the requirements to proceed to examination. It follows several years of environmental assessment, technical development and engagement with communities, landowners, local authorities, businesses and other stakeholders in the project area. 
Acceptance does not amount to planning approval or development consent. Instead, it marks the start of the pre-examination stage, during which members of the public and other stakeholders will be able to register as Interested Parties and participate in the process. The application will subsequently be examined independently, after which the Planning Inspectorate will make a recommendation to the Secretary of State for Energy Security and Net Zero. The Secretary of State will make the final decision on whether development consent should be granted. 
National Grid said feedback gathered during consultation had helped shape the proposals and informed continuing design work. The company said engagement would continue as the project progresses through the planning process. 
The proposed investment could also create opportunities for businesses and suppliers across East Yorkshire, North Lincolnshire and neighbouring areas. National Grid identified potential demand for a range of services and skills associated with major infrastructure delivery, including engineering, construction, environmental consultancy, logistics, accommodation, catering and professional services. 
If the project receives development consent, National Grid has proposed establishing a community fund worth around £18 million. The fund would support locally identified priorities, potentially including community facilities, environmental improvements, health and wellbeing initiatives and energy efficiency projects. The arrangements would be developed with residents, charities, community groups and elected representatives, in line with government guidance. 
The acceptance of the DCO application is a procedural milestone for the proposed transmission link, rather than confirmation that construction can begin. The project must pass through examination and receive a decision from the Secretary of State before it can secure the development consent required to proceed.