SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

MMRDA’s Atal Setu–Mumbai–Pune Expressway link road project reaches 67% completion

#Infrastructure News#Infrastructure#India#Maharashtra#Mumbai City
Synopsis

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 67% of the physical work on the 7.35-km, six-lane elevated link road connecting Atal Setu with the Mumbai–Pune Expressway. The project is expected to reduce travel time between South Mumbai and Pune by approximately 60–90 minutes once operational. It will also ease congestion at Panvel junction and improve connectivity to Navi Mumbai International Airport, Pune, Goa and Jawaharlal Nehru Port. Construction is progressing across the Chirle and Palaspe sections, with foundation and structural works at different stages of completion. The project forms part of MMRDA’s broader regional connectivity strategy under its ‘Mumbai in 59 Minutes’ vision.

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved 67% physical progress on the 7.35-km, six-lane elevated link road connecting Atal Setu, also known as the Mumbai Trans Harbour Link, with the Mumbai–Pune Expressway. The project, which is being developed through the Chirle and Palaspe sections, is intended to provide a direct connection between the two major road corridors, reduce congestion at Panvel junction and improve regional connectivity. 
Once operational, the elevated road is expected to save approximately 60–90 minutes on journeys from South Mumbai to Pune, depending on prevailing traffic conditions. It will also provide a more direct route between Mumbai, Navi Mumbai and the Mumbai–Pune Expressway, extending the connectivity benefits created by Atal Setu towards Pune and Goa. 
Atal Setu has improved road connectivity between Mumbai and Navi Mumbai, making it easier to access emerging economic, industrial and logistics centres across the Mumbai Metropolitan Region. However, increasing vehicle movement towards Pune, Goa and Jawaharlal Nehru Port has added pressure on the existing road network, particularly around Panvel's main junction, where traffic from Atal Setu merges with other major highways. 
To address this constraint, MMRDA is developing a separate six-lane elevated corridor through Chirle and Palaspe. The route is designed to allow vehicles to bypass the congested junction and access the Mumbai–Pune Expressway more efficiently. A key engineering feature is the construction of the elevated road at a third level above existing roads and bridge infrastructure, enabling more effective use of available road space while maintaining traffic movement on the existing network. 
Construction is progressing across both sections. In the Chirle section, foundation work, comprising 113 piles and 42 open foundations, has been completed. Column construction has reached 98%, with 153 of the planned 155 columns erected. Girder casting and fabrication are largely complete, while deck slab work has reached 49%, covering 117 of the 240 spans. Reinforced earth (RE) wall panel casting is 90% complete, and work on the railway overbridge (ROB) section has reached 85%. 
In the Palaspe section, 15 of the 21 pile-group foundations have been completed, taking progress to 71%. Column casting has reached 38%, while girder casting has been completed. Reinforced earth wall panel work is 90% complete, and construction of the railway overbridge section is progressing. 
The link road is expected to reduce dependence on Panvel's main junction and improve traffic movement between the Mumbai–Pune Expressway and the Mumbai–Goa Highway. It will also strengthen connectivity towards Navi Mumbai International Airport and improve access to commercial and logistics areas in the surrounding region. 
The project is expected to improve the movement of passengers and freight on National Highway 48 (NH-48), which connects Mumbai, Pune and Bengaluru, and National Highway 348 (NH-348), which provides access to Jawaharlal Nehru Port Authority (JNPA). Improved links between Mumbai, Navi Mumbai, Pune, Goa and key industrial and logistics centres are also expected to support regional economic activity. 
The project is aligned with MMRDA’s broader ‘Mumbai in 59 Minutes’ vision, which aims to integrate metro corridors, expressways, tunnels, ring roads and missing links into a connected regional transport network. Rather than developing individual infrastructure projects in isolation, the authority is focusing on linking existing and upcoming corridors to improve journey times and accessibility across the Mumbai Metropolitan Region. 
Maharashtra Chief Minister Devendra Fadnavis said the state’s future economic growth would depend on how efficiently its cities, industries, ports and emerging development centres were connected. He noted that Atal Setu had already improved connectivity between Mumbai and Navi Mumbai, while the expressway link road would extend these benefits to Pune and create faster connectivity between two important economic centres. He added that reducing travel time and improving freight and logistics efficiency were central to developing infrastructure that could attract investment and support balanced regional growth. 
Deputy Chief Minister and MMRDA Chairman Eknath Shinde said the benefits of major infrastructure projects should translate into tangible improvements for commuters. He stated that the new link road would extend Atal Setu’s connectivity benefits towards Pune, Goa and other destinations, while reducing congestion around Panvel. The anticipated time savings, he said, would provide commuters with greater convenience and improve efficiency for businesses and industries. 
MMRDA Metropolitan Commissioner Dr Sanjay Mukherjee said achieving 67% physical progress marked an important stage in the implementation of the project. He noted that foundation and column construction in Chirle was largely complete, while major structural components in Palaspe were progressing. He added that the link road would address an important missing connection between Atal Setu and the Mumbai–Pune Expressway, improving traffic management and reducing pressure on existing junctions. The project, he said, was another step towards MMRDA’s integrated regional connectivity approach under its ‘Mumbai in 59 Minutes’ vision.