The Bangalore Metro Rail Corporation Limited (BMRCL) has moved a step closer to mainline testing on the Blue Line, with a trial train running from the Baiyappanahalli depot towards KR Puram and Doddanekundi, Bengaluru Development Minister Krishna Byre Gowda confirmed. Kinematic test runs are expected this month, and BMRCL aims to run trial trains up to Marathahalli by 15 November, although signalling integration remains the main hurdle. The Silk Board-KR Puram section is targeted for May 2027, and the full line to the airport for March 2028.
Representative image
The Bangalore Metro Rail Corporation Limited (BMRCL) has moved a step closer to mainline testing on the Blue Line, with trial runs progressing from the Baiyappanahalli depot towards KR Puram and Doddanekundi, Bengaluru Development Minister Krishna Byre Gowda confirmed, Swarajya reported.
Advertisement
The minister shared the update on Deepavali, saying the government is committed to completing all pending works and bringing the Blue Line into public service at the earliest. A trial run was held on 10 November on the up line, extending testing done between the depot and Benniganahalli on 7 November. The latest run took the train through the KR Puram section towards Doddanekundi, according to a Vijay Karnataka report cited by Urban Acres.
Kinematic test runs are expected in November 2026. The line’s 33 kV cables and third rail are being charged progressively from 30 October between the depot and Marathahalli. BMRCL’s managing director, PC Jaffer, told Moneycontrol earlier that the corporation aims to run trial trains from the depot via KR Puram to Marathahalli by 15 November. He said all work had been completed except signalling, with about 2 km of track and construction at some stations still pending. BEML has delivered two trainsets for the line, which he said is enough to begin trials.
Signalling is the key hurdle, since it must be integrated with the trains and other systems before full testing can begin. Jaffer said that the opening of the lines depends on how fast the testing can be done, and BMRCL aims to finish its work by March 2027.
The Blue Line is being built in two parts with a total length of 58.19 km, under Phases 2A and 2B of Namma Metro at an estimated cost of Rs 14,788 crore. Phase 2A runs for 19.75 km from Central Silk Board to KR Puram, with 13 elevated stations. Phase 2B runs for 38.44 km from KR Puram to Kempegowda International Airport via Hebbal. The first package of Phase 2A, covering six elevated stations, KR Puram, Mahadevapura, DRDO Complex, Doddanekkundi, ISRO and Marathahalli, has been completed. The entire corridor will have 29 stations. It connects with the Purple Line at KR Puram, the Yellow Line at Central Silk Board and the Pink Line at Nagawara.
The timeline has slipped repeatedly. The line was originally meant to be completed in 2024. In June, when the first train arrived at the depot, officials said trials were months away because the track was not ready. Trial runs on the Silk Board-KR Puram stretch are now planned to lead to opening of that section by May 2027. The airport end is now targeted for March 2028, three months later than the earlier December 2027 date, according to a Swarajya report of August.
This disclaimer ("Disclaimer") is applicable to the entire Site. Upon entering the Site it is recommended that you immediately read the Terms and Conditions and Privacy Policy listed therein. Your continued usage of this Site will indicate your unconditional acceptance of the said Terms and Conditions and Privacy Policy. You hereby agree that Prop News Time reserves the right to modify at any time, the Terms and Conditions and Privacy Policy governing this Site without prior notification. Your usage of the Site implies that you will be bound by any such modification. You agree and acknowledge that it is your responsibility to periodically visit the Site and stay updated with the Terms and Conditions and Privacy Policy of the Website.
The information contained in this Site has been provided by Prop News Time for information purposes only. This information does not constitute legal, professional or commercial advice. Communication, content and material within the Site may include photographs and conceptual representations of projects under development. All computer-generated images shown on the Site are only indicative of actual designs and are sourced from third party sites.
The information on this Site may contain certain technical inaccuracies and typographical errors. Any errors or omissions brought to the attention of Prop News Time will be corrected as soon as possible. The content of this Site is being constantly modified to meet the terms, stipulations and recommendations of the Real Estate Regulation Act, 2016 (“RERA”) and rules made thereunder and may vary from the content available as of date. All content may be updated from time to time and may at times be out of date. Prop News Time accepts no responsibility for keeping the information on this website up to date or any liability whatsoever for any failure to do so.
While every care has been taken to ensure that the content is useful, reliable and accurate, all content and information on the Site is provided on an "as is" and "as available" basis. Prop News Time does not accept any responsibility or liability with regard to the content, accuracy, legality and reliability of the information provided herein, or, for any loss or damage caused arising directly or indirectly in connection with reliance on the use of such information. No information given under this Site creates a warranty or expands the scope of any warranty that cannot be disclaimed under applicable law.
This Site provides links to other websites owned by third parties. Any reference or mention of third-party websites, projects or services is for purely informational purposes only. This information does not constitute either an endorsement or a recommendation. Prop News Time accepts no responsibility for the content, reliability and information provided on these third-party websites. Prop News Time will not be held liable for any personal information or data collected by these third parties or for any virus or destructive properties that may be present on these third-party sites.
Your use of the Site is solely at your own risk. You agree and acknowledge that you are solely responsible for any action you take based upon this content and that Prop News Time is not liable for the same. All details in the form of news stories, photos and videos provided on this Site are updated on the basis of information available from the respective developers/owners/promoters. All such information will not be construed as an advertisement. This Site is for guidance only. Your use of this Site – including any suggestions set out in the Site and or any use of the resources available on this Site, do not create any professional–client relationship between you and Prop News Time. Prop News Time cannot accept you as a client until certain formalities and requirements are met.
Cookie Disclaimer
We use cookies to give you the best possible service while using our website, please accept it and continue browsing if you're happy with this. For more information see our Privacy Policy
Advertise With Us
Subscribe to PNT News
Are you sure you want
to delete your account?
This action is final. Once your account and all associated personal data has been deleted, you have to again register and all your data will be lost.