SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

NextDC pauses uncontracted data centre projects after Melbourne setback

#International News#Industrial#Australia
Synopsis

Australian data centre operator NextDC has suspended work on projects that do not have customer contracts, following delays and community opposition affecting its flagship M3 expansion in Melbourne. Chief Executive Craig Scroggie said securing local support and restoring confidence in the project would take priority before the company resumed work on other developments. NextDC, which had 11 data centres in development or planning, did not specify how many projects would be affected. The decision follows a 42% fall in its share price after the company reduced its earnings forecasts last month. Meanwhile, Goodman Group and Digital Realty have acquired a 9.9% stake in NextDC for approximately USD 492 million, although both investors said they were not currently seeking control of the company.

Australian data centre operator NextDC has paused work on projects without customer contracts after delays and community opposition disrupted its flagship M3 data centre expansion in Melbourne, prompting the company to prioritise securing local support and restoring confidence in the development. Chief Executive Craig Scroggie announced the decision at the UBS Australasia conference on Monday, following a 42% fall in NextDC's share price after it cut its earnings forecasts last month.


The M3 expansion has faced delays linked to power supply constraints and community opposition. The setback forced NextDC to revise its financial outlook and raised concerns about the company's development pipeline. Scroggie said the recent difficulties reflected wider challenges facing the data centre sector, including community concerns about artificial intelligence and the physical infrastructure required to support it.

He said winning community backing for the Melbourne project was now the company's primary focus. Developments without customer contracts or firm customer commitments would no longer be treated as priorities until the issues surrounding M3 had been addressed. Scroggie did not disclose the number of projects that would be suspended.

NextDC had 11 data centres either under development or in the planning stages, according to its 2026 annual report. The company will not restart the affected work until it has communicated how it intends to resolve the problems and rebuilt the trust of stakeholders who have supported its projects. Scroggie indicated that the company would need to demonstrate that it had addressed the concerns before returning to its wider development programme.

The decision comes as opposition to data centre developments has become a challenge for operators seeking to expand capacity to meet rising demand for digital infrastructure and artificial intelligence computing. Power availability and the impact of large facilities on surrounding communities have become important considerations for projects, including NextDC's Melbourne expansion.

The company's difficulties have also attracted investment from two major industry players. Goodman Group and its New York-listed partner Digital Realty acquired a 9.9% stake in NextDC for approximately USD 492 million, equivalent to AUD 715 million, following the decline in its share price. NextDC's stock subsequently recovered the ground lost after the earnings downgrade.

Scroggie said the recent challenges had created an opportunity for investors to consider taking a position in the company. Goodman and Digital Realty said they were not currently planning to make a takeover offer, although they reserved the right to do so.

The two investors said they wanted to work with NextDC rather than seek control, and indicated that they would welcome discussions with its board and management about potential ways to help address the company's challenges. Their investment therefore places them among NextDC's significant shareholders as the Australian operator reviews its development priorities.

The immediate focus for NextDC remains the M3 project and the restoration of community support. The suspension of uncontracted work marks a change in the company's development approach as it seeks to address project delays before progressing with its wider pipeline.

Source - Reuters