The Haryana Real Estate Regulatory Authority has dismissed a homebuyer's claim seeking approximately INR 1 crore in compensation and legal costs from Ireo Grace Realtech over a delayed apartment in its Corridors project in Sector 67A, Gurugram. The adjudicating officer held that the buyer could not seek compensation after the authority had previously found him to be a payment defaulter and ordered a refund subject to deductions. The dispute involved an apartment booked in 2013, with possession originally scheduled for January 2018. The promoter argued that the buyer had stopped paying instalments despite repeated reminders.
The Haryana Real Estate Regulatory Authority (HRERA) has dismissed a compensation claim of approximately INR 1 crore filed by a homebuyer against Ireo Grace Realtech over an apartment in its Corridors residential project in Sector 67A, Gurugram. The adjudicating officer held that compensation could not be granted after the authority had previously determined that the buyer was at fault for defaulting on payment instalments.
The complainant, Gagan Deep Singh, had booked an apartment measuring approximately 1,726.9 sq ft in the project in 2013. He signed the builder-buyer agreement on April 3, 2014, for a total consideration of around INR 1.70 crore and paid approximately INR 48.4 lakh under a construction-linked payment plan.
Possession was scheduled for January 11, 2018. However, the developer received the occupation certificate only on January 27, 2022. The buyer had stopped making further payments, citing delays in construction, following which the developer cancelled the apartment on September 1, 2016.
The buyer subsequently approached HRERA, seeking relief against the cancellation and recovery of the amounts paid. In an order dated February 8, 2024, the authority directed Ireo to refund the amount received after deducting 10% of the sale consideration as earnest money, along with interest at 10.8% per annum calculated from the date of cancellation.
The buyer then filed a separate complaint before the adjudicating officer, seeking INR 50 lakh as compensation for alleged harassment and default, another INR 50 lakh towards litigation expenses, and a refund with 24% interest. He also contended that a settlement agreement signed on July 15, 2024, had not been honoured in its intended manner.
Ireo opposed the claim, stating that construction had been affected by force majeure circumstances and that the buyer had failed to pay instalments despite repeated reminders and opportunities. The promoter also argued that the settlement had addressed the buyer's outstanding claims and that the agreed payment, along with the applicable tax deduction, had been completed.
In dismissing the compensation complaint on October 7, 2026, Adjudicating Officer Rajender Kumar observed that the Haryana RERA Rules, 2017, allow compensation proceedings where the authority has first established a violation by the promoter. In this case, the earlier order had found the buyer responsible for payment defaults and had directed a refund subject to the prescribed deduction.
The adjudicating officer therefore held that compensation could not be awarded in the absence of an established promoter violation in the earlier proceedings. The dismissal does not alter the refund direction issued in February 2024, which had already addressed the buyer's claim concerning the cancelled apartment.
The case highlights the distinction between a developer's delay in obtaining project approvals and a homebuyer's compliance with contractual payment obligations. Although the occupation certificate was obtained after the scheduled possession date, the compensation claim was dismissed on the basis of the findings in the buyer's earlier proceedings.