Canadian resource company Millennial Potash is targeting construction of its Banio potash project in Gabon by the end of 2027 or early 2028, subject to securing financing and obtaining the required mining permit. The project, backed by the US International Development Finance Corporation for feasibility studies, has an estimated initial capital expenditure of USD 480 million. Growing interest from potential buyers and financiers could prompt the company to increase planned annual production from 800,000 tonnes to as much as 1.2 million tonnes.
Canadian resource company Millennial Potash is targeting the start of construction at its Banio potash project on Gabon's southern coast by the end of 2027 or early 2028, with the possibility of increasing its planned annual production capacity to 1.2 million metric tonnes amid growing interest from prospective buyers and financiers.
The company is advancing a definitive feasibility study for the project alongside environmental and social impact assessments, Millennial Potash Chairman Farhad Abasov told Reuters. The project is expected to require an initial capital investment of approximately USD 480 million.
The US International Development Finance Corporation (DFC) has committed USD 3 million towards the project's feasibility study. Millennial Potash is working to finalise a broader funding package with the DFC and other potential partners, with the objective of achieving financial close by August or September 2027. Reaching financial close within this timeframe would support the company's construction target.
Before mining can begin, Millennial Potash must also convert its existing exploration licence into a mining permit. The process is expected to commence in the first quarter of 2027 and could take between three and six months, according to Abasov.
The project timeline will depend on the completion of these regulatory and financing milestones. If construction begins towards the end of 2027 or in early 2028, the company estimates that it will take approximately 18 to 24 months to commence production.
Once operations begin, Millennial Potash expects to ramp up output to its initially targeted annual capacity of 800,000 metric tonnes within six months. However, the company is considering a larger initial production scale in response to interest from prospective offtakers and financiers.
Abasov indicated that the company could evaluate starting production at an annual capacity of 1 million to 1.2 million metric tonnes instead of the original 800,000-tonne target. Such an increase would depend on the company's assessment of market demand, financing arrangements and the project's development requirements.
The chairman said prospective offtakers included groups from the United States, Brazil, Asia and Africa. He did not disclose the identities of these potential buyers or provide details of the volumes they may be willing to purchase.
Potash is an important raw material used in the manufacture of certain fertilisers, making production capacity and access to buyers significant considerations for the project's commercial development.
The proposed Banio development remains subject to the completion of feasibility and environmental studies, conversion of the exploration licence, and the securing of financing. Millennial Potash's ability to meet its construction schedule and determine the project's eventual production capacity will depend on progress across these areas.
Source: Reuters