SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Haryana RERA rejects additional compensation claim by Emaar plot buyers over delayed possession

#Law & Policy#Land#India#Haryana
Synopsis

The Haryana Real Estate Regulatory Authority’s Adjudicating Officer has dismissed a claim for additional compensation by buyers of a plot in Emerald Floors Premier at Emerald Estate, Sector 65, Gurugram, holding that allottees who continue with a project and accept possession are entitled to interest for the delay rather than separate compensation for the same cause. In Suresh Rawat and another v Emaar India Limited, Adjudicating Officer Rajender Kumar noted that the buyers had already received interest at 9.40 per cent annually for the delayed possession period. The buyers had sought about INR 73.9 lakh for mental agony, legal expenses and loss of rental income.

The Adjudicating Officer of the Haryana Real Estate Regulatory Authority (HRERA), Gurugram, has dismissed a complaint seeking additional compensation for delayed possession of a residential plot in Emerald Floors Premier at Emerald Estate, Sector 65, Gurugram. The authority held that allottees who remain in a project and accept possession are entitled to interest for the period of delay, and cannot claim separate compensation for the same cause of action. 
In Suresh Rawat and another v Emaar India Limited (Complaint No. 775 of 2026), Adjudicating Officer Rajender Kumar observed that the complainants had already been granted delayed-possession interest by the authority. He said an allottee who does not withdraw from a project is entitled to interest for every month of delay until possession is handed over. The order held that there was no basis for granting separate compensation for the same delay after the earlier relief had been awarded. 
The buyers had booked a 1,650 sq yd plot in Emerald Floors Premier in September 2009. The builder-buyer agreement was executed on 14 January 2010 for a consideration of INR 87.61 lakh, while the buyers paid INR 88.71 lakh. Possession was due by 14 January 2013 but was offered by Emaar India Limited only on 17 January 2020. The buyers took possession on 9 March 2020. 
In an earlier proceeding, the authority had granted the buyers interest at an annual rate of 9.40 per cent for the period from 14 January 2013 to 17 March 2020. The buyers subsequently approached the adjudicating officer seeking further compensation. Their claim included INR 15 lakh for mental agony and physical suffering, INR 3 lakh towards legal expenses and INR 55.90 lakh for loss of rental income, taking the total claim to approximately INR 73.9 lakh. 
The buyers' counsel argued that additional compensation could be awarded under Section 72 of the Real Estate (Regulation and Development) Act, 2016. Emaar India opposed the claim, submitting that the buyers had accepted possession and had already received INR 53.32 lakh in September 2025. The company also relied on the Haryana Real Estate Appellate Tribunal's decision in Tata Housing Development Company Limited v Nitin Singhal and Surendra Kumar Singhal, which had taken a similar view on claims for additional compensation following delayed possession. 
The adjudicating officer dismissed the complaint, relying on the principle that an allottee who continues with a project and accepts possession is entitled to delayed-possession interest for the period of delay. The ruling addresses the buyers' claim for additional compensation after the earlier award of interest in this case. 
Source Haryana Rera