SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Bombay High Court refuses relief to developer over 18-year delay in Mumbai redevelopment project

#Law & Policy#Infrastructure#India#Maharashtra#Mumbai City
Synopsis

The Bombay High Court has declined to grant relief to Om Shanti Properties, which challenged the termination of its appointment as developer for the redevelopment of Parijat Cooperative Housing Society in Kalachowkie. The project, involving 181 society members, had remained stalled for nearly 18 years. The court stressed that developers have a legal responsibility to complete redevelopment within a reasonable timeframe, observing that homeownership involves emotional as well as financial investment. The society terminated its agreement in February 2025 and appointed a new developer in September 2026.

The Bombay High Court has refused to grant relief to Om Shanti Properties (OSP), which challenged the termination of its appointment as developer for the redevelopment of Parijat Cooperative Housing Society in Mumbai’s Kalachowkie after the project remained incomplete for nearly 18 years. The court said developers have a legal responsibility to deliver flats within a reasonable timeframe, noting that buying a home involves emotional and financial investment for residents. 
A division bench of Chief Justice Mahesh Chandra Tripathi and Justice Advait Sethna made the observations in an order passed on October 26, while considering the developer’s plea against the society’s termination notice dated February 11, 2025. OSP had sought to have the notice set aside and its redevelopment rights restored. The project was originally awarded in 2008 with the majority consent of the society’s members. 
The court observed that prolonged delays in redevelopment projects increase the difficulties faced by tenants, flat owners, occupants and other beneficiaries, while undermining the purpose of redevelopment laws. It said developers must account for the expectations attached to homeownership and ensure that their obligations to hand over flats are fulfilled on time. The bench also noted that redevelopment projects involve commercial benefits and incentives, including additional floor space index, and cannot be allowed to remain pending indefinitely on one pretext or another. 
The Parijat society has 181 members and the redevelopment covers two buildings, a chawl, 19 garages, two temples, a gymnasium and two godowns. The erstwhile partners of OSP were appointed developers on March 31, 2008. The Brihanmumbai Municipal Corporation issued a show-cause notice in 2017 over the lack of progress and terminated the redevelopment contract on July 16, 2018. 
The civic body allowed OSP to resume the project in February 2019 after it paid a capital value of INR 27.68 crore. The court was informed that the developer had agreed to terminate the project if it was not completed by 2022. However, progress remained stalled after 2020. The BMC subsequently sought to terminate the letter of intent and blacklist the developer. 
In June 2024, OSP executed permanent alternative accommodation agreements with society members. The society nevertheless terminated the development agreement in February 2025 and decided to appoint another developer. It appointed a new builder in September 2026. 
OSP argued that the delay could not be attributed entirely to it, stating that implementation depended on several steps involving the society and the BMC. The society, however, maintained that the developer had failed to advance the project for almost two decades. It also argued that the INR 27.68-crore payment made by OSP after repeated defaults did not create any equity or entitlement for the developer to retain the project. 
The High Court declined to restore OSP’s position, leaving the society’s decision to move ahead with a new developer undisturbed. The ruling leaves the society free to proceed with its newly appointed developer. 
Source- Bombay High Court