Finnish police have launched a criminal investigation into suspected environmental law violations at the site of a planned Google data centre near Muhos in northern Finland. The investigation concerns forest clearing, drainage and water management activities allegedly carried out before the completion of mandatory environmental impact assessments. The site is being developed by Tuike Finland, a subsidiary of Google's parent company Alphabet. The investigation follows an October order by Finland's Supervisory Agency to halt preparatory work at two locations. Google has said it will cooperate with authorities.
Finnish police have launched a criminal investigation into suspected environmental law violations at the construction site of a planned Google data centre near Muhos in northern Finland. The investigation centres on forest clearing, drainage and water management activities allegedly carried out by Tuike Finland, a subsidiary of Google's parent company Alphabet, before the completion of the environmental impact assessments required under Finnish law.
The project is part of Google's planned investment of USD 15 billion in artificial intelligence infrastructure in Finland, announced last month. The company described the investment as its largest in Europe. The proposed development is part of a wider plan to expand its data centre capacity and support services including Gemini, Search, Maps and YouTube.
Detective Superintendent Kari Pakanen told Reuters that police were investigating whether the company's activities had violated Finland's Water Act and caused environmental damage. He said a finding of guilt could result in a corporate fine. However, he declined to disclose whether any individuals could become targets of the investigation.
According to a police statement, preliminary findings had identified ambiguities and shortcomings in drainage and water management at Tuike Finland's site. Police said they would provide an update in December, while the investigation is expected to continue into 2027.
The investigation follows an order issued by Finland's Supervisory Agency (LVV) on October 6, directing Google to stop preparatory activities that could alter the environment at the Muhos site and another location. The agency is responsible for overseeing environmental permits and assessments.
Pakanen said the decision on whether work could resume at the data centre sites would rest with LVV. A spokesperson for the agency said it was not yet clear how long the approval process would take before the relevant permits could be granted.
A Google spokesperson said the company would cooperate with the police investigation and continue to focus on maintaining compliance at its sites. The company also said it had worked closely with the Finnish government and local communities on infrastructure projects for more than a decade and was responding to enquiries from LVV and other authorities.
Finland has emerged as one of Europe's major destinations for data centre investments, supported by its cool climate, low-carbon electricity supply and government backing for artificial intelligence infrastructure. The country, which is similar in size to Germany but has a population of fewer than 6 million, has also experienced less public opposition to data centre developments than some other markets, including the United States.
However, the expansion of data centres is expected to increase electricity demand in the country. Grid operator Fingrid has projected that Finland's electricity consumption could rise by up to 40% in the coming years if all agreed grid connection projects move ahead. Artificial intelligence data centres are among the main factors behind the projected increase.
Google's planned investment in Finland extends beyond data centre construction. It also includes improvements to the electricity grid, clean energy projects and battery developments intended to supply power for its digital services.
Finnish Prime Minister Petteri Orpo supported Google's investment plan when it was announced last month, describing it as a boost to the country's economy. He also played down concerns that the expansion could increase electricity demand and push up power prices. The Prime Minister's Office did not immediately respond to Reuters' request for comment on the investigation.
The investigation raises questions about the environmental approval process for large-scale data centre developments in Finland, particularly as the country attracts more investment in artificial intelligence infrastructure. The outcome could affect the timeline for Google's planned projects at the two locations, as work cannot resume without the necessary regulatory permissions. With electricity demand also expected to increase as more data centres are developed, balancing infrastructure expansion with environmental compliance and resource management remains an important issue for Finland's data centre sector.
Source Reuters
12th Nov, 2026