A villa project in Koheda village near Hyderabad has continued construction despite three official notices over alleged encroachment on feeder channels supplying Chinna Cheruvu lake. Irrigation and revenue officials found that portions of the development extended into the water body's maximum flood level area and buffer zone. Inspections in September 2025 identified basements, villas and other structures in the affected areas. Despite repeated communications seeking action against the alleged violations, construction has reportedly continued. Residents raised the issue again with the state government on October 6, 2026.
A villa project in Koheda village, in Telangana's Rangareddy district, has continued construction despite repeated notices from government departments over alleged encroachment on feeder channels connected to Chinna Cheruvu lake, raising concerns about enforcement of water-body protection regulations.
The project is located in Abdullapurmet mandal and spans survey numbers 155, 156, 159, 160, 161, 163, 164 and 167. According to irrigation department officials, streams and a canal passing through survey number 156 flow from south to north and act as feeder channels for Chinna Cheruvu, identified as Hyderabad Metropolitan Development Authority (HMDA) lake ID 1962 near Pedda Amberpet.
In a communication dated October 6, 2026, N Vijender Reddy, deputy executive engineer of Irrigation Sub-Division-3, Hyderabad, informed the Abdullapurmet tahsildar that the development had allegedly encroached on the feeder channel. The communication also stated that the developer had not obtained a no-objection certificate (NOC) or prior permission from the irrigation department.
The department first inspected the site on September 15, 2025. Officials reported that portions of the project had come up within the maximum flood level (MFL) area and the buffer zone of the feeder channel. The inspection report warned that construction in these areas could obstruct the natural movement of water and increase the risk of inundation in upstream locations.
A second joint inspection involving irrigation and revenue officials took place on September 25, 2025. Using village maps and topographical sheets, the mandal surveyor identified a canal running through survey number 156. The joint inspection report stated that the developers had not made adequate provisions for the existing streams and that feeder channels had been encroached upon.
The report identified 11 basements with pillars, seven villas, a compound wall and an office building within the MFL area and buffer zone. These findings formed the basis for subsequent communications seeking action against the alleged violations.
Following the inspections, the irrigation department wrote repeatedly to the Abdullapurmet tahsildar, the Turkayamjal municipal commissioner and authorities in the Adibhatla municipal zone. Communications issued in February 2026 and again in October sought cancellation of the layout and villa project approvals and called for appropriate enforcement measures. However, officials said construction had continued despite the repeated notices.
The case has also drawn the attention of local residents, who raised the issue during the state government's Prajavani public grievance programme on October 6. The complaint was subsequently forwarded to the irrigation department and the Rangareddy district collector for further action.
The alleged encroachment raises concerns about the protection of natural drainage channels, particularly during heavy rainfall. Blocking or narrowing feeder channels can disrupt water flows and increase flooding risks in surrounding and upstream areas.
The next steps depend on the response of the district administration and municipal authorities to the irrigation department's communications. The status of the project's approvals and the alleged encroachments remains to be addressed by the concerned authorities.