Karnataka Power Transmission Corporation Limited has commissioned a 12-km 220 kV multi-circuit transmission line in Bengaluru, officials said on Tuesday. The line provides double Line-In Line-Out connectivity to existing 220 kV lines from the cable terminating tower near the Bagalur Road crossing, and uses part of the available transmission alignment in the Vidyanagar area. Officials said it will strengthen the city's grid capacity and operational reliability and help meet growing power demand. Karnataka Energy Minister K J George said Bengaluru's demand is continuously increasing.
Karnataka Power Transmission Corporation Limited (KPTCL) has commissioned a 12-km-long 220 kV multi-circuit transmission line in Bengaluru, officials said on Tuesday. The corporation described it as another milestone in strengthening the city's transmission network. The line provides double Line-In Line-Out (LILO) connectivity to existing 220 kV transmission lines, identified in reports as the Hoodi-HBR Layout and ITI-Manyata Tech Park lines, from the cable terminating tower near the Bagalur Road crossing, KPTCL said in a statement. A LILO arrangement connects a new point to an existing line by cutting the line and routing it in and out of that point.
As part of the project, a portion of the available transmission alignment in the Vidyanagar area was technically utilised to construct the multi-circuit line. A multi-circuit line carries more than one electrical circuit on the same set of towers, which can reduce the land and corridor space needed in built-up areas. KPTCL said developing transmission infrastructure in densely populated urban areas requires careful consideration of space constraints, existing electrical networks, roads and other urban infrastructure. For this project, it said, the local conditions, technical feasibility and operational requirements were comprehensively assessed before an appropriate engineering design and execution method was adopted.
KPTCL Managing Director V Ram Prasath Manohar said the local conditions and technical requirements of the project were unique. He said successfully commissioning the line amid existing electrical and urban infrastructure reflects the technical competence, coordination and commitment of the corporation's engineers and field teams.
Officials said the new transmission system will strengthen Bengaluru's grid capacity and operational reliability, and improve the network's ability to meet the city's growing power demand. Karnataka Energy Minister K J George said power demand in Bengaluru is continuously increasing and that transmission infrastructure must be strengthened accordingly.
State-level data show how quickly demand has grown. Karnataka's maximum demand was 14,367 MW in 2020-21, 14,818 MW in 2021-22, 15,828 MW in 2022-23 and 17,220 MW in 2023-24, and it reached about 18,385 MW in 2024-25, according to figures given by the then KPTCL managing director.
Bengaluru Electricity Supply Company Limited (BESCOM), which distributes power in the city, has estimated an electric vehicle charging load of about 363.54 MW by 2030 and has been expanding charging infrastructure beyond its existing 209 stations, according to an earlier report.
KPTCL has used compact designs for urban lines before. In January 2018, it built a 220 kV line through the Jigani industrial area using monopoles, which allowed the line to be laid in the median of a road with a narrow width of 1.5 metres, according to an industry publication. KPTCL is Karnataka's state transmission utility, responsible for carrying electricity from generating stations to distribution companies such as BESCOM. Manyata Tech Park, in north Bengaluru, is one of the city's large technology campuses. The statement did not disclose the project's cost or the additional power it can carry.