The Haryana Real Estate Regulatory Authority (HRERA) has directed Ocean Seven Buildtech Pvt Ltd to pay delayed possession interest at 10.8% annually to 12 homebuyers of its Expressway Towers project in Sector 109, Gurugram. The interest will apply from the revised possession deadline of 30 May 2022 until a valid offer of possession or actual handover, subject to the conditions specified in the order. The authority also restricted certain charges and directed the developer to issue revised account statements.
The Haryana Real Estate Regulatory Authority (HRERA) has directed Ocean Seven Buildtech Pvt Ltd to pay interest at 10.8% per annum to 12 homebuyers of its Expressway Towers affordable housing project in Sector 109, Gurugram, over delays in handing over their flats. The order, dated 29 September 2026, was passed by HRERA chairman Arun Kumar.
The authority held that the developer had failed to deliver the housing units by the revised deadline of 30 May 2022. The interest will be calculated on the amounts paid by the allottees from that date until a valid offer of possession, followed by two months after the occupation certificate is obtained, or actual handover, whichever occurs earlier.
The 10.8% rate comprises the State Bank of India's marginal cost of lending rate of 8.8%, plus an additional two percentage points, as prescribed under Rule 15 of the Haryana RERA Rules. The homebuyers had sought interest from 26 September 2020, but the authority determined the applicable possession deadline under the Affordable Housing Policy, 2013.
Under the policy, affordable housing projects must be completed within four years of the later of the building plan approval or environmental clearance. For Expressway Towers, environmental clearance was granted on 30 November 2017. A six-month extension granted during the Covid-19 pandemic extended the deadline to 30 May 2022.
The authority noted that the developer had not filed a reply despite being given several opportunities to do so, and the proceedings were consequently conducted ex parte. It also observed that the available records did not establish that the promoter had applied for an occupation certificate or provided an update on the project's construction status. The authority therefore treated the project as ongoing.
The order requires Ocean Seven Buildtech to pay the accrued interest arrears within 90 days. The developer must subsequently pay monthly interest before the 10th of each month and issue revised statements of account within 30 days. Homebuyers must clear any outstanding dues after receiving the revised statements. The developer is also required to complete possession and execute conveyance deeds within three months of obtaining the occupation certificate.
The authority further restricted the recovery of certain charges from buyers. It prohibited the developer from levying labour cess and work contract tax, observing that homebuyers are neither employers nor contractors for this purpose. Value-added tax may be recovered only where legally applicable, on an actual and proportionate basis, with supporting proof of payment and subject to the developer's tax scheme. Maintenance and utility charges must be based on actual consumption, in line with the Haryana Department of Town and Country Planning's January 2024 clarification.
The ruling adds to the regulatory scrutiny surrounding Expressway Towers, where homebuyers have faced prolonged delays in receiving possession. The authority's directions establish the interest payable to the 12 complainants while setting out conditions for the recovery of charges and completion of the possession process.