Georgia’s B3 Arch Bridge has reached a key construction milestone following the completion of concrete pouring for the final section of the left half of its arch ring. The bridge is being built by China Railway 23rd Bureau Group Co. Ltd. under Lot 2 of the Georgia North–South Corridor Road Project. Measuring 437.875 metres in total length, it has a main arch span of 286 metres and stands 164 metres above the valley floor. The full arch ring is expected to close by the end of 2026.
Georgia’s B3 Arch Bridge has achieved a key construction milestone with the completion of concrete pouring for the final section of the left half of its arch ring. The bridge, part of Lot 2 of the Georgia North–South Corridor Road Project, is being constructed by China Railway 23rd Bureau Group Co. Ltd. The full arch ring is expected to be closed by the end of 2026. With a main arch span of 286 metres, the bridge is set to become the largest-span cast-in-situ concrete arch bridge in the Caucasus region.
The milestone was achieved on October 20 in the Khada Gorge of the Caucasus Mountains. The B3 Arch Bridge is a key structure along Georgia’s North–South Corridor, where difficult terrain has made road construction challenging. Its completion is expected to improve connectivity between northern and southern Georgia.
The bridge has a total length of 437.875 metres, a clear main arch span of 286 metres and a deck positioned 164 metres above the valley floor. It features a deck-type reinforced concrete arch design with two separate box-section arch ribs. Construction is being carried out using a cable-stayed buckling system and cantilever casting with form travellers.
The project team has faced challenging weather and geographical conditions during construction. The site experiences persistent strong winds, winter temperatures as low as minus 20 degrees Celsius and snow depths of up to two metres. These conditions require careful attention to the bridge’s wind resistance, structural durability and construction accuracy.
Another technical challenge is the arch ring’s relatively small cross-section, measuring 3.5 metres in width and 4.7 metres in height. According to the project announcement, these are the smallest cross-sectional dimensions among comparable long-span arch bridges. The slender design increases the difficulty of cantilever casting and maintaining precise alignment throughout construction.
To address the challenges, the project management team worked with a university in China to conduct full-life-cycle wind tunnel tests and on-site verification of wind resistance. The work helped establish a wind-resistance monitoring and safety assurance system covering both the construction and operational stages.
The team also maintained strict controls over construction methods, quality checks and the geometry of the arch ring. The left half of the arch was closed with high precision, and all relevant indicators comply with European design standards, according to the announcement.
Once completed, the B3 Arch Bridge will become the largest-span reinforced concrete arch bridge in the Caucasus region. Its 286-metre main arch span is also expected to rank among the leading examples worldwide of comparable arch bridges constructed using cantilever casting.
As a key structure on Georgia’s North–South Corridor, the bridge is expected to remove a major bottleneck in road transport across the Caucasus Mountains. It is also expected to reduce travel times between northern and southern Georgia, improve transport efficiency and road safety, and strengthen the region’s integrated road network.
The project is part of wider infrastructure cooperation between China and Georgia under the Belt and Road Initiative. Improved road connectivity is expected to support regional trade and economic activity along the corridor.
The construction team will now focus on the remaining bridge works, with continued attention to safety, quality and progress. The immediate target is to complete the full arch ring by the end of 2026. The date for opening the entire road project to traffic has not been specified in the announcement.
The bridge’s progress highlights the engineering challenges involved in building major road infrastructure through the Caucasus Mountains, where severe winters, strong winds and difficult terrain affect construction. Its next major milestone is the planned closure of the entire arch ring by the end of 2026. After that, the remaining construction work will need to be completed before the road project can open to traffic. The opening date remains unannounced, making the progress of the remaining works an important point to monitor.
Source PTI