Families relocated from Kochi's flood-prone P&T Colony to a rehabilitation complex in Mundamveli continue to face housing problems despite government spending on the project. Built by the Greater Cochin Development Authority (GCDA) under the LIFE Mission scheme, the apartments have developed cracks, water seepage and wastewater leaks, raising concerns about residents' safety. The project has also faced questions over a high-voltage power line passing above the site and delays in transferring land ownership. Meanwhile, families identified for other housing projects remain without homes because of pending documentation and allocation delays.
Residents of P&T Colony in Kochi, who spent decades moving to temporary rehabilitation camps whenever heavy rain flooded their homes, continue to face housing difficulties after being shifted to an apartment complex in Mundamveli. The Greater Cochin Development Authority (GCDA) constructed the complex under the Kerala government's LIFE Mission housing scheme to rehabilitate families living along the flood-prone Thevara-Perandoor canal. However, construction defects have raised concerns about whether the apartments are safe to occupy.
The project, built on 70 cents of GCDA-owned land, was handed over to residents on January 31, 2024. Residents reported cracks in walls and wastewater from toilets on upper floors leaking into apartments below. Abhilash Parameswaran, a resident and president of the action council for P&T apartment residents, said the families had raised these issues with GCDA and the state government but had yet to receive a satisfactory resolution.
Residents have also raised concerns about a 110-kilovolt power line passing above the apartment complex. According to Parameswaran, the line poses a safety risk and has created technical difficulties in transferring land ownership to the beneficiaries. He also alleged irregularities in the project's implementation and claimed that former GCDA chairpersons were aware of the issues. These remain allegations. Former GCDA chairman C N Mohanan said the project was conceived to provide better housing to families who regularly faced flooding and lacked basic facilities. He acknowledged that there had been failures in ensuring that the complex was constructed without defects.
GCDA officials said a state government committee had approved the project design and that the authority was prepared to carry out repairs. However, an official said residents had demanded a 50-year guarantee for the building after the repair work. The dispute has added to the delay in finding a lasting solution for the families living in the complex.
The problems extend beyond P&T Colony. RAY Towers 1 and 2, inaugurated in September 2025, were intended to provide homes to identified beneficiaries in Kochi. However, the city corporation had still not allotted the apartments to families a year after the inauguration. Of the 398 beneficiaries identified earlier, documentation remained pending for around 100 families.
Kochi mayor V K Minimol said the corporation was working to obtain police clearance certificates for 297 families whose details had been collected. She added that 33 families on the beneficiary list had said they did not require homes in the complex, requiring the corporation to identify around 100 additional families to fill the remaining vacancies. The corporation was completing minor works and planned to hand over the units to 297 families by November 1, 2026.
Residents of Santhipuram Colony near Palarivattom are also waiting for housing. The previous Left Democratic Front (LDF)-led administrative council announced a housing project, but its tenure ended four months later without substantial progress on construction. The United Democratic Front (UDF)-led council, which took office in December 2025, had not made significant progress on building homes for the colony's residents by the time of the report.
The P&T apartment complex has faced further scrutiny over its condition. A report submitted to the Kerala High Court by a court-appointed amicus curiae flagged wastewater leakage, water seepage, corrosion and concerns about the sewage system. The report recommended urgent relocation of residents to safe accommodation and an expert assessment of the building's structural stability. Separately, the Kerala State Commission for Protection of Child Rights registered a case over the conditions faced by children living in the complex.
The situation in Kochi highlights the challenges involved in delivering rehabilitation housing that remains safe, legally transferable and ready for occupation. For the P&T Colony complex, the immediate priorities are an independent assessment of structural safety, a clear repair or relocation plan and resolution of the land ownership issue. For beneficiaries awaiting homes at RAY Towers and Santhipuram Colony, the next test is whether pending documentation, allocation and construction work can be completed within stated timelines. The outcome will depend on coordinated action by the authorities responsible for these projects.
11th Nov, 2026