Central Railway has sought forest clearance to divert approximately 6.5 hectares of forest land for the proposed 32.23-km fourth railway line between Kalyan and Asangaon in Maharashtra. Estimated to cost INR 1,619.96 crore, the project is proposed to be funded equally by the Railways and the Maharashtra government. The additional line is intended to increase capacity along the busy corridor, which carries suburban trains, long-distance passenger services and freight traffic. The proposal remains subject to the necessary forest clearance before the project can proceed.
Central Railway has sought approval to divert approximately 6.5 hectares of forest land for the proposed fourth railway line between Kalyan and Asangaon, a 32.23-km infrastructure project aimed at increasing capacity on one of the region’s heavily used railway corridors. The application has been submitted through the Centre’s Parivesh portal, initiating the process for obtaining the forest clearance required to take the project forward.
The proposed line is estimated to cost INR 1,619.96 crore, with the expenditure to be shared equally by the Railways and the Maharashtra government. The forest land identified for diversion falls within the Thane and Shahapur forest divisions. The proposal remains subject to the necessary approval from the central government before the land can be used for railway infrastructure.
The Kalyan–Asangaon section currently has two electrified railway tracks, while construction of a third line is under way. Suburban local trains, long-distance mail and express services, and freight trains operate along the same corridor. The additional line is intended to provide more capacity for these different services and improve operational flexibility on a route where the availability of tracks limits the scope for accommodating additional traffic and managing disruptions.
The proposed fourth line will largely run parallel to the existing and planned railway tracks, making use of the Railways’ existing right of way wherever possible. The alignment is planned to pass through Kalyan, Shahad, Ambivli, Titwala, Khadavali, Vasind and Asangaon. Railway yards at Kalyan, Titwala, Khadavali, Vasind and Asangaon are also proposed to be connected to the new line.
Project documents state that shifting the alignment away from the existing railway corridor is not considered feasible, as doing so could increase the overall land requirement. Non-forest land has been used wherever possible to limit the extent of forest land diversion. However, the proposed use of forest land means the project must secure the required statutory clearance before the affected land can be used for non-forestry purposes.
The fourth line forms part of Central Railway’s broader capacity-augmentation efforts to address congestion and improve the movement of suburban, passenger and freight services beyond Kalyan. The corridor faces particular constraints where different categories of trains share the available tracks, limiting operational flexibility.
The forest clearance application marks a procedural step in the project’s progress, but it does not mean that permission for the proposed diversion has already been granted. The project’s further progress will depend on the applicable approvals and implementation process.