Mumbai airport's phased Terminal 1 redevelopment is set to put pressure on available capacity, with Adani Airports beginning the shutdown of sections of the terminal from January. Airlines will have the flexibility to shift operations to T2, Navi Mumbai International Airport (NMIA) or other airports during the redevelopment, said Arun Bansal, CEO Adani Airport Holdings. Mumbai International Airport Ltd has planned the first phase of T1 demolition for January 15, 2027 with traffic redistributed to T2 and NMIA ahead of the shutdown.
Mumbai airport's phased Terminal 1 redevelopment is set to put pressure on available capacity, with Adani Airports beginning the shutdown of sections of the terminal from January. Airlines will have the flexibility to shift operations to Mumbai Airport T2 if there is availability, Navi Mumbai International Airport (NMIA) or other airports during the redevelopment, according to the airport operator.
Arun Bansal, CEO, Adani Airport Holdings, said the operator cannot delay the redevelopment as the existing terminal needs to be demolished and rebuilt. "From the beginning of January, one-third of T1 will be shut down. Two-thirds a little later and further ahead, the entire T1 will be shut down and redeveloped." Bansal said.
The phased closure will require airlines to accommodate operations elsewhere. Bansal said carriers could move to NMIA or other airports depending on their operational requirements. "They have a choice to go anywhere or stop operations. When the NOTAM is over, when the terminal is back, they can start." he said.
The airport operator will not dictate where airlines move their operations, Bansal said. "We can never tell airlines. Airlines have to make their own decisions based on their business logic," he said.
Adani Airports has given airlines advance notice to plan for the shutdown. "We have to tell them in advance. So, they have around six months of planning," Bansal said. He also ruled out delaying the demolition in response to airline requests. "They say can you delay the T1 demolition? We say sorry, cannot" he said. Bansal said the redevelopment is necessary given the condition of the existing terminal and the need to create modern capacity at Mumbai airport. The operator has told airlines they can move to Navi Mumbai whenever they want, while feedback from carriers on infrastructure is being addressed.
Mumbai International Airport Ltd (MIAL) has planned the first phase of T1 demolition for January 15, 2027 with traffic redistributed to T2 and NMIA ahead of the shutdown.
The capacity pressure will coincide with changes to Mumbai airport's cargo operations. Adani Airports expects all freighter operations to move to NMIA before October 15, however sources indicate this timeline will see delays. The existing cargo terminal at Mumbai airport will also need to be rebuilt with the redevelopment expected to take around three years. "We need to tear down cargo. We have to make a new cargo terminal which will take three years." Bansal said.
T1, one of Mumbai airport's two passenger terminals, primarily handles domestic operations, and its closure is expected to concentrate more passenger and cargo traffic at T2 during the redevelopment window. NMIA, which began commercial operations in the region more recently, is being positioned by the operator as an alternative outlet for airlines and cargo operators seeking to avoid congestion at Mumbai airport during the multi-year construction period, even as the operator works to expand ground infrastructure and passenger facilities to absorb the shift in traffic.
Source- Adani Newsroom