Kolkata Metro’s Orange Line has moved closer to reaching Salt Lake Sector V after the first push trolley inspection was completed on the Beleghata-IT Centre section. The inspection followed the completion of the viaduct and ballastless track works, allowing electrical works to begin on the stretch. The section forms the third phase of the 32-km Kavi Subhash-Jai Hind Bimanbandar Metro corridor. A 366-metre viaduct gap at Chingrighata on EM Bypass had delayed progress for several years. The Beleghata-Sector V section is currently being targeted for commissioning by December 31, 2026.
Kolkata Metro’s Orange Line has crossed a major construction hurdle on the route to Salt Lake Sector V, with the first push trolley inspection completed on the Beleghata-IT Centre section of the Kavi Subhash-Jai Hind Bimanbandar Metro corridor. The inspection was carried out on September 17 after the completion of viaduct and ballastless track works, clearing the section for electrical works.
The Beleghata-IT Centre stretch forms the third phase of the 32-km Orange Line corridor, which was sanctioned in 2010 and is being implemented in five phases. The first two sections, connecting Kavi Subhash with Hemanta Mukhopadhyay and Hemanta Mukhopadhyay with Beleghata, are already operational. The latest section will extend services towards the IT and commercial district of Salt Lake Sector V and provide an interchange with the existing Green Line at Sector V.
The main construction constraint on this section was the 366-metre gap at Chingrighata on EM Bypass. The final 31-metre concrete deck slab was placed in August, completing the viaduct across the previously unfinished stretch. Concrete girders had been erected across the Chingrighata crossing over two weekends in May 2026, with traffic diverted through a new road constructed by Rail Vikas Nigam Limited.
The Orange Line currently operates over around 9 km between Kavi Subhash, also known as New Garia, and Metropolitan at Beleghata. The completion of the Chingrighata viaduct has now allowed track-related works to advance across the previously disconnected section towards Sector V. With the viaduct and ballastless track works completed, electrical installation is the next major stage before testing and other commissioning-related activities.
All three new stations on the Beleghata-IT Centre section and the viaduct connecting the stations have been constructed, according to the latest project update. The reported target is to commission the section by December 31, 2026. Once operational, the extension is expected to allow passengers to travel from New Garia to Sector V in around 30 minutes, improving direct metro connectivity between the southern part of Kolkata and the Salt Lake IT district.
The wider Kavi Subhash-Jai Hind Bimanbandar corridor is planned to connect southern Kolkata with the airport through a combination of elevated and other sections. The Orange Line’s expansion towards Sector V will also strengthen its connection with the Green Line, which links Sector V with Howrah Maidan. This will create an additional interchange option for passengers travelling between the city’s southern areas, Salt Lake and the central-western parts of Kolkata.
The latest inspection therefore marks the transition of the Beleghata-Sector V section from major civil and track construction towards electrical and systems-related works. While the track is now ready for trains to be moved along the stretch for subsequent testing, passenger operations will depend on the completion of electrical, signalling, safety and commissioning procedures. The December 31 target remains the reported timeline for starting services on this section.
Source PTI