Kerala Agriculture Minister T Siddique has said that all houses in the Wayanad rehabilitation township for survivors of the 2024 Mundakkai-Chooralmala landslide will be completed by 31 October. Keys to 178 first-phase houses have been handed over, and 177 families have moved in. The 157 second-phase houses are under construction, with basic amenities due by December. Roads will follow after the rains subside, and the houses will be handed over by lottery once conditions allow. Survivors had protested in Kalpetta over what they described as slow progress.
Kerala Agriculture Minister T Siddique has said that construction of all houses in the Wayanad rehabilitation township for survivors of the 2024 Mundakkai-Chooralmala landslide will be completed by 31 October. The minister said the work was progressing as scheduled and was being regularly reviewed at various levels.
He was responding to reporters after survivors protested in Kalpetta, alleging that construction was moving slowly. The survivors said they were still living in rented houses and that the financial assistance provided by the government was not enough to meet their expenses.
Keys to 178 houses in the first phase of the township were handed over to families on 1 March, ahead of the Kerala Assembly elections this year. The minister said 177 families have moved into their homes, while one house remains unoccupied because of an ongoing court case.
In the second phase, 157 houses are under construction across various clusters. Around 110 of them were expected to be completed by the end of September, with the rest by 31 October, according to the minister. Township authorities said painting of the 149 houses designated for immediate handover is under way and is expected to be completed by 31 October, and that another eight houses are being built for allotment once the government publishes the final list of beneficiaries. About 900 workers are engaged on site, officials said.
The minister said the draw of lots for allotment is not linked to the construction work, and that it can be held immediately once construction is complete and conditions are suitable for handing the houses over. Road construction within the township, which had caused difficulty for first-phase residents because of muddy conditions, is to begin by early November after the rains subside and be completed by December. Officials said the 149 families will receive their houses only after the roads are ready.
Siddique said all basic amenities in the township would be completed by December. Construction of the commercial centres is entering its final phase, and the hospital building is also progressing, with both expected to be completed before the New Year. The school and the parade ground planned for the township will not be taken up immediately.
The minister said steps have been initiated to include survivors left out of the first list of eligible beneficiaries because of technical issues, and that a second lottery covering them will be held soon.
The township is being built on 64.47 hectares at Elstone Estate near Kalpetta, which the government took over in April 2025 after depositing INR 44.33 crore in court. The foundation stone was laid on 27 March 2025. The project provides houses of about 1,000 sq ft on seven-cent plots for families affected by the landslide of 30 July 2024, which hit Mundakkai, Chooralmala and nearby areas.