Nashik's civic and Kumbh authorities are pushing dozens of road and bridge works ahead of the Simhastha Kumbh Mela 2027, which opens with a flag-hoisting ceremony on 31 October 2026. The Nashik Municipal Corporation lists 38 sanctioned works on its website, including road corridors and five bridge projects. The Nashik-Trimbakeshwar Kumbh Mela Authority has directed departments to finish identified works before the ceremony and submit milestone-based schedules. Media reports said around 70 per cent of work on major road and bridge projects was pending in early September, against a March 2027 deadline.
The Nashik-Trimbakeshwar Kumbh Mela Authority (NTKMA) and the Nashik Municipal Corporation (NMC) are accelerating road and bridge works ahead of the Simhastha Kumbh Mela 2027, which formally begins with a flag-hoisting ceremony at Ramkund in Nashik and Kushavart in Trimbakeshwar on 31 October 2026.
At a review meeting on 6 August, chaired by NTKMA Commissioner Shekhar Singh, departments were directed to complete the identified works well before the ceremony. Singh said no project should remain unfinished when it takes place. NMC Commissioner Manisha Khatri attended, along with officials of the Maharashtra State Infrastructure Development Corporation, the Water Resources Department, the Public Works Department, the State Archaeology Department and the Trimbak Municipal Council. The review covered the Ram Kal Path and adjoining roads at Ramkund, water supply in Trimbakeshwar, restoration of Kushavart Kund, Darshan Path works, Dhwajastambha-related works and the road from Gajanan Maharaj Sansthan to Ambedkar Chowk. Departments were asked to submit detailed progress reports and milestone-based completion schedules, and to flag issues needing inter-departmental coordination.
The NMC's website lists 38 sanctioned Simhastha Kumbh works, on a page last updated on 8 September. They include road corridors such as Gangapur Road from Bardan Phata to Sula Chowk, Trimbak Road from Papaya Nursery signal to Ex-lo junction, Pune Road from Datta Mandir Chowk to Sinnar Phata, and the outer bypass between Pathardi Phata and Pimpalgaon Khamb. The bridge works are Milind Nagar, Lakshmi Narayan Mandir, the Tapovan STP bridge over the Godavari, the Nandini river bridge on Trimbak Road at Pimpalgaon Bahula, and the down-ramp of the Sant Gadge Maharaj bridge. The list also covers the Ganeshwadi curtain wall, Tapovan hospital and Indira Gandhi hospital.
Media reports point to a large remaining workload. The Free Press Journal reported on 1 September that about 70 per cent of work on 35 major road and bridge projects was pending, with the Milind Nagar bridge over the Nasardi river around 45 per cent complete and a March 2027 deadline. Swarajya reported earlier that NTKMA and the NMC had told contractors to fast-track 28 road works across 120 km, estimated at INR 1,270 crore, and had warned of show-cause notices and penalties for delays. Construction World reported approval of 32 road projects worth INR 13.5 billion, with white-topping targeted for completion by December 2026. The figures differ because the reports cover different or overlapping scopes.
The state government had earlier approved the Nashik Ring Road and the widening of the Nashik-Trimbak Road to six lanes. The Maharashtra Public Works Department records this at a meeting chaired by Chief Minister Devendra Fadnavis with Union Road Transport Minister Nitin Gadkari on 22 June 2025.
Source: Nashik Municipal Corporation