The Nagpur Municipal Corporation (NMC) is preparing a detailed project report to assess the city's water requirements until 2047, with a water grid, a possible supply link through the proposed Wainganga-Nalganga river-linking project and greater wastewater reuse among the options under consideration. The exercise aims to address future demand as the city's population grows beyond the existing planning horizon of 2031. A proposed barrage on the Kanhan river is also part of the broader water-security strategy, alongside measures to improve the use of treated sewage.
The Nagpur Municipal Corporation (NMC) is drawing up a long-term water supply strategy to meet the city's requirements until 2047, extending its existing planning horizon by 16 years. The civic body is preparing a detailed project report (DPR) to assess future demand and examine additional sources of water as Nagpur's population and urban footprint expand.
Standing Committee chairperson Shivani Dani Wakhare said the existing water supply plan is based on an estimated population of 30 lakh until 2031, with a prescribed requirement of 135 litres per capita per day. The NMC is now assessing the infrastructure and resources needed to serve the city over the following decades.
Three broad measures are being examined. The first involves developing a water grid along the periphery of the proposed third outer ring road in the Nagpur Metropolitan Region Development Authority (NMRDA) area. The proposed network is intended to strengthen the city's distribution and supply infrastructure as development expands towards the metropolitan region.
The second option is to explore sourcing water during the monsoon through the proposed Wainganga-Nalganga river-linking project. Estimated at INR 94,912 crore, the scheme envisages transferring surplus water from the Wainganga basin towards the Nalganga in the Tapi basin. However, the quantity that could be made available for Nagpur's municipal requirements, the infrastructure needed to transport it and the arrangements for sharing the resource would need to be established before it can become a dependable supply source.
The third measure involves expanding wastewater recycling and exploring water-swapping arrangements, alongside the proposed Kolar-Kanhan barrage. Nagpur currently recycles around 423.5 million litres per day (MLD) of sewage water, of which approximately 390 MLD is supplied to the Koradi and Khaparkheda thermal power plants. Greater reuse for suitable non-potable purposes could reduce dependence on fresh water for industrial requirements and help reserve more of it for domestic consumption.
The proposed Kolar-Kanhan barrage near Bina village in Kamptee taluka is estimated to cost INR 952.32 crore. The planned 438-metre structure is expected to have a live storage capacity of 67.81 million cubic metres. Its detailed project report and design have been prepared by the Central Designs Organisation, Nashik, and the proposal has been submitted to the state government for administrative approval. Funding arrangements and land-related processes remain unresolved.
The long-term planning exercise comes as reservoir storage levels have declined. On October 29, Totladoh reservoir held 356.22 million cubic metres, representing 35.03 per cent of its designed live storage capacity, compared with 94.05 per cent on the corresponding date last year. The combined live storage of Totladoh, Navegaon Khairy and Khindsi stood at 477.71 million cubic metres, or 37.87 per cent of their combined capacity.
The NMC's existing planning norm translates to a calculated requirement of 405 MLD for a population of 30 lakh, while the civic body currently supplies around 770 MLD. This difference requires a detailed assessment of consumption, distribution efficiency and water losses; it cannot automatically be treated as wasted water.
The proposals remain under examination, with approvals, funding and implementation arrangements yet to be finalised. The DPR is expected to help establish the city's long-term requirements and identify the measures needed to strengthen water security through 2047.