The Bihar Road Construction Department has set 2028 as the completion target for the 14.5-km Ramnagar-Kachchi Dargah section of the Patna Ring Road, a six-lane corridor being developed under NH-131G at an estimated cost of INR 1,183 crore. The project is being executed in Engineering, Procurement and Construction mode and is intended to strengthen Patna’s peripheral road network while providing an alternative route for heavy vehicles that currently use roads within the city. The state government has directed engineers to maintain construction schedules and quality standards as work progresses.
The Bihar Road Construction Department has reviewed the progress of the 14.5-km Ramnagar-Kachchi Dargah section of the Patna Ring Road and retained 2028 as the target for completion. The six-lane corridor is being developed under NH-131G through the Engineering, Procurement and Construction model at an estimated cost of INR 1,183 crore. The review was conducted as part of an assessment of major road projects in Patna and other districts, with officials focusing on construction progress, implementation issues and adherence to project schedules. Road Construction Department Secretary Pankaj Kumar Pal directed engineers involved in the project to maintain the construction timeline while ensuring that prescribed quality standards are followed during execution.
The Ramnagar-Kachchi Dargah corridor forms part of the wider Patna Ring Road network, which is being developed to strengthen connectivity around the state capital and provide an alternative route for traffic travelling around the city. According to the department, the completed corridor will allow heavy vehicles to bypass Patna rather than entering the city through its major arterial roads. This is intended to reduce pressure on existing urban routes, particularly where through traffic currently mixes with local movement. The 14.5-km section therefore represents one component of a wider peripheral road system rather than an isolated urban road project, with its eventual utility dependent on the progress of connecting sections of the ring road network.
The project is being implemented as a six-lane highway and is being constructed in EPC mode. The department’s review also covered a number of other road projects across Bihar, including the Chausa-Buxar bypass, Daudnagar bypass on NH-139, the four-lane Bhagalpur-Dhaka Mor road up to Kharhara village and the Arwal bypass on NH-139. Officials also assessed the proposed four-lane road from Kharhara in Bhagalpur to Bhaljore near the Bihar-Jharkhand border, the Bettiah bypass on NH-727 and proposed bypass projects at Madhepura and Singheshwar on NH-131. The review indicates that the Ramnagar-Kachchi Dargah section is being progressed alongside a broader programme of road connectivity projects across the state.
The wider Patna Ring Road is planned as a peripheral road network connecting areas around the capital and extending across parts of Patna, Saran and Vaishali districts. Other sections of the network include the Kanhauli-Sherpur corridor and the Sherpur-Dighwara Ganga bridge and its approaches, which are being developed as separate components of the larger system. The Sherpur-Dighwara section includes a six-lane bridge across the Ganga and is intended to connect Patna with North Bihar. The Ramnagar-Kachchi Dargah section will connect into this wider network, although its 2028 target should be read specifically as the completion timeline reported for this 14.5-km package.
For Patna, the planned corridor is expected to add capacity to the city’s outer road network while separating a portion of longer-distance and heavy-vehicle movement from traffic using urban roads. The department has emphasised timely completion and construction quality as work advances, with engineers asked to address project-level issues and adhere to stipulated schedules. The 2028 target places the Ramnagar-Kachchi Dargah section within the broader timeline for development of the Patna Ring Road, with the effectiveness of the corridor ultimately linked to the completion and integration of other sections. The project’s progress will therefore remain relevant not only for the 14.5-km stretch itself but also for the wider peripheral connectivity planned around Patna.