SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Mumbai’s GMLR Dindoshi-Film City flyover targets October 15 opening

#Infrastructure News#Infrastructure#India#Maharashtra#Mumbai City
Synopsis

The nearly 1.3 km flyover connecting Dindoshi Court with Dadasaheb Phalke Chitranagari, or Film City, in Mumbai is expected to open to traffic by October 15, 2026, as part of the wider Goregaon-Mulund Link Road (GMLR) project. The main civil construction has been completed, including all 31 piers and 30 spans, along with girder installation, deck slab casting and construction of approach roads on both sides. The Brihanmumbai Municipal Corporation (BMC) is now completing finishing works and other requirements ahead of the proposed opening. A load test is scheduled for the second week of October to assess the structure’s safety and carrying capacity before it is opened to motorists.

The six-lane flyover runs from the Dindoshi Court area, turns near Ratnagiri Junction Hotel and descends at Film City. The structure forms part of the 12.2 km GMLR corridor, which is being developed to provide a direct east-west connection between the Western Express Highway and Eastern Express Highway. The wider project includes twin tunnels beneath Sanjay Gandhi National Park and between Tulsi and Vihar lakes, a box tunnel section in Film City, bridges and interchanges. Once the complete corridor is operational, the project is intended to reduce the road travel time between Mumbai’s eastern and western suburbs from around 75 minutes to about 25 minutes. 
Several works remain to be completed on the flyover before it can be opened. These include finishing activities, road markings, signage, installation of electrical poles and noise barriers. Officials have also been instructed to complete the 7.5 metre-wide slip roads alongside the flyover, remove barricades from the roads below the structure and clear construction debris and solid waste from the site. The BMC has asked its teams to coordinate with traffic police so that vehicle movement can be managed once the flyover is opened. The proposed October 15 traffic opening will therefore follow completion of these works as well as the required technical procedures and load testing. 
The Dindoshi-Film City flyover is an important component of the GMLR project because it is being brought into operation ahead of the full 12.2 km corridor. The flyover will provide a direct elevated connection between the Dindoshi side of the Western Express Highway and Film City, while the remaining GMLR components will progressively establish the wider east-west link. The corridor includes substantial underground infrastructure, with twin tunnels planned beneath Sanjay Gandhi National Park and between Tulsi and Vihar lakes. The project has therefore been divided into multiple components, with the flyover forming one of the sections that can be commissioned separately from the complete corridor. 
With the major structural work now complete, the focus has shifted to testing, finishing and traffic-readiness measures. The load test planned for the second week of October will be followed by the remaining technical procedures before the BMC allows public traffic on the flyover. The October 15 target remains subject to completion of these requirements. Once operational, the flyover will add a direct connection between Dindoshi and Film City and form an operational section of the larger GMLR network, while the remaining tunnels, bridges, interchanges and other components continue towards completion.