The Nashik Municipal Corporation (NMC) has started laying underground multi-utility ducts beneath 19 major roads that are being upgraded ahead of the 2027 Nashik-Trimbakeshwar Simhastha Kumbh Mela. The ducts are designed to accommodate seven essential services, including water supply, drainage, optical fibre cables, piped natural gas, electricity and stormwater infrastructure. NMC plans to complete the utility work by the end of February and commence road development on the 19 priority stretches by the end of March. The civic body is targeting completion of all 29 approved Kumbh-linked road projects by March 2027.
The Nashik Municipal Corporation (NMC) is installing underground multi-utility ducts before undertaking major road upgrades planned for the 2027 Nashik-Trimbakeshwar Simhastha Kumbh Mela, with the system being introduced across 19 priority roads to prevent newly constructed surfaces from being repeatedly excavated for utility repairs.
The integrated ducts will accommodate seven essential services, including water supply, drainage, optical fibre cables (OFC), piped natural gas supplied through Maharashtra Natural Gas Ltd (MNGL), electricity cables of Maharashtra State Electricity Distribution Company Ltd (MSEDCL) and stormwater lines. By placing these networks below the carriageways in a planned utility corridor, NMC intends to allow future repairs and service upgrades without cutting into the completed roads.
NMC commissioner Manisha Khatri has directed officials and contractors to accelerate the duct work so that the associated road projects can proceed within the planned schedule. The civic body has set the end of February as the deadline for completing the utility ducts and plans to begin work on the 19 roads by the end of March. All the road projects have been targeted for completion by March 2027, ahead of the Simhastha Kumbh Mela.
The Kumbh Mela Authority has approved 29 road projects in Nashik with a combined value of around INR 1,200 crore. Work orders have already been issued for 19 projects, while the process for awarding the remaining 10 is underway. The utility duct system is being implemented first on the priority stretches so that road construction does not have to be followed by repeated excavation for underground services.
Among the roads included in the first phase are Gangapur Road from Bardan Phata to Sula Chowk, estimated at INR 56.86 crore; Trimbak Road from Papaya Nursery to XLO Junction, at INR 77.33 crore; XLO Junction to Garware Chowk, at INR 71.99 crore; Vihitgaon to Godavari Ghat through Bytco Chowk and Jail Road, at INR 65.50 crore; and the Nandur Naka Bridge to Jatra Hotel stretch, at INR 71.20 crore.
Most of the major stretches in the programme are planned to use white-topping technology, which involves providing a concrete surface over the road structure to improve durability and reduce the frequency of major maintenance. The utility ducts are intended to complement this approach by protecting the upgraded road surface from future excavation.
The decision comes as Nashik undertakes a wider infrastructure programme for the Simhastha Kumbh Mela. The Nashik divisional administration has separately recorded administrative approvals for road and ancillary works within the NMC area, including a package of 21 works valued at INR 930.23 crore, alongside other road works being undertaken through the Public Works Department.
By completing underground utility infrastructure before the major road works, NMC is attempting to address a recurring urban infrastructure problem: newly upgraded roads being dug up soon afterwards to install or repair essential services. The approach is expected to reduce disruption to traffic, simplify future maintenance and preserve the condition of the roads during and after the Kumbh-related infrastructure programme.