Central Railway has completed all works on the railway span of Mumbai’s reconstructed Sion Road Overbridge, taking the project into its final stage. The new 54.5-metre single-span structure is 29 metres wide and comprises two semi-through steel girders, each weighing around 500 tonnes. The railway portion was executed as part of the CSMT-Kurla fifth and sixth lines project under MUTP-II B. The Brihanmumbai Municipal Corporation is currently undertaking approach road works, with the complete bridge expected to be ready by September 30, subject to the required arrangements with concerned authorities.
Central Railway has completed the railway-side works for the reconstructed Sion Road Overbridge (ROB) in Mumbai, bringing the long-delayed project closer to reopening and restoring an important east-west road connection in the Sion area. The bridge, which had missed its earlier August 15 target, is now expected to be completed by September 30, with approach works being carried out by the Brihanmumbai Municipal Corporation (BMC). The full structure will be opened to road traffic after the remaining works and necessary arrangements with the concerned authorities are completed.
The railway portion of the new bridge consists of a 54.5-metre single span with an overall width of 29 metres. It has two semi-through steel girder assemblies with reinforced cement concrete deck slabs, supported on 1,200-mm-diameter pile foundations and pile caps. The new single-span configuration replaces the earlier two-span arrangement and has been designed to provide the space required for the proposed fifth and sixth railway lines between CSMT and Kurla.
A key part of the reconstruction involved the fabrication, assembly and launching of two large steel girders across the operational railway corridor. Each girder weighs around 500 tonnes. Their launching was carried out in stages during June and August, with the work requiring coordination between construction, operating and electrical departments. Planned traffic and power blocks were used to carry out critical activities while limiting disruption to railway operations. After the girders were placed on their permanent supports, deck slab construction and the remaining railway-span works were completed.
The original Sion bridge was constructed in 1912 and extended on either side in 1980. After more than a century of service, the structure had developed distress, leading to its reconstruction. The replacement is intended to address the ageing structure while also accommodating the additional railway tracks planned as part of the CSMT-Kurla fifth and sixth lines project under Mumbai Urban Transport Project-II B. The additional lines are expected to increase rail capacity and provide greater operational flexibility on the busy suburban corridor.
While the railway span is complete, work on the road approaches remains in progress. The BMC is responsible for these works within the civic limits, which need to be completed before the entire bridge can be opened to traffic. The reopening is also linked to the reconstruction of the Dharavi Road Overbridge, with traffic department permission for its closure to be granted after the Sion ROB is completed.
The completion of the railway span marks the transition from the major structural works over the railway corridor to the final road and connectivity-related works. Once the approaches and associated arrangements are completed, the reconstructed Sion ROB is expected to restore the road connection while supporting the wider expansion of railway infrastructure between CSMT and Kurla.