SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Delay in nod for phase-II tender holds up new metro work in Gurugram

#Infrastructure News#Infrastructure#India#Haryana#Gurugram
Gurugram News Desk Last Updated : 21 Sep 2026
Synopsis

A 2.2-km stretch of the Gurugram Metro's Phase I corridor, between Hero Honda Chowk and Umang Bhardwaj Chowk, remains held up by delays in utility shifting, with Gurugram Metro Rail Limited (GMRL) setting a November 2026 deadline to clear the right-of-way. The clearance of this stretch has become critical not only for maintaining progress on Phase I but also for the evaluation of the Phase II tender, currently under review by senior officials of GMRL and the Haryana Mass Rapid Transport Corporation (HMRTC), with the pending approval holding up the start of new construction work on the extended corridor.

Delays in shifting utilities along a key 2.2-km stretch of the Gurugram Metro corridor are holding up progress on both the ongoing Phase I construction and the approval process for the Phase II tender, with Gurugram Metro Rail Limited (GMRL) now targeting November 2026 to clear the affected right-of-way. 
The stretch in question runs between Hero Honda Chowk and Umang Bhardwaj Chowk, a section identified as one of the key construction bottlenecks along the corridor. The Gurugram Metro project will cover about 28.5 km in total, from Millennium City Centre to Cyber City, and has been planned in two phases. Phase I covers approximately 15.22 km of elevated metro from Millennium City Centre to Sector 9, including a spur towards the Dwarka Expressway, with 14 stations along the route. Construction is progressing across other sections of Phase I, with GMRL planning to begin U-girder launching by the end of August 2026. 
Phase II is planned to extend the metro from Sector 9 to Cyber Hub, covering a further 13 km and connecting with both the Rapid Metro and the Namo Bharat Rail Corridor through an interchange at Shankar Chowk. The World Bank has approved a loan of INR 1,409 crore for this phase, which carries an estimated overall project cost of around INR 2,700 crore. 
The tender for Phase II is currently under evaluation by senior officials of GMRL and the Haryana Mass Rapid Transport Corporation (HMRTC). Officials have indicated that clearance of the Hero Honda Chowk-Umang Bhardwaj Chowk stretch is critical not just for maintaining momentum on Phase I, but also for the corridor's continued progress through one of its more significant construction bottlenecks, with the pending resolution of utility shifting in this stretch closely tied to the broader approval timeline for new work under Phase II. 
Phase II has faced earlier delays as well, including an initial holdup linked to finalising the location of the penultimate station near Shankar Chowk, an issue that has since been resolved. The Phase II tender for the depot in Sector 33, estimated at approximately INR 409 crore, was separately reissued after only one bidder was found eligible under the earlier round. 
Once complete, the combined Gurugram Metro corridor will span roughly 30.7 km with 28 stations and a depot in Sector 33, with two additional spurs, one towards Sector 102 near the Dwarka Expressway, and another towards Gurugram railway station. GMRL has set August 2028 as the completion deadline for Phase II, though officials have said timely progress will depend on continued coordination among supporting agencies, particularly on outstanding issues such as the relocation of power substations and drainage infrastructure along parts of the alignment.