SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

BMC targets 2029 completion for Kurla-Mahim stretch of Mithi River revamp

#Infrastructure News#Infrastructure#India#Maharashtra#Mumbai City
Synopsis

The Brihanmumbai Municipal Corporation (BMC) has set a December 2029 target to complete the INR 1,800-crore third package of the Mithi River rejuvenation project, covering the stretch from Kurla's CST Road bridge to Mahim Causeway. The project will combine flood-control infrastructure with sewage interception through 18 gate-pump systems, a major pumping station, retaining walls and service roads. Around 2,000 families will require rehabilitation, making resettlement one of the biggest challenges in delivering the integrated river restoration project on schedule.

The Brihanmumbai Municipal Corporation (BMC) has accelerated work on the Kurla-Mahim stretch of the Mithi River rejuvenation project, targeting December 2029 for completion of the INR 1,800-crore third package that combines flood mitigation, sewage management and riverbank strengthening. 
The project covers the stretch between CST Road bridge in Kurla and Mahim Causeway, one of the most vulnerable sections of the river corridor where tidal backflow and untreated sewage have contributed to recurring flooding and environmental degradation. 
A central feature of the project is the installation of 18 gate-pump systems at strategic locations along the river. The gates will prevent seawater from flowing back into the river and adjoining drainage network during high tide, while the pumps will help remove excess rainwater during periods of intense rainfall. According to civic officials, the system is expected to provide significant flood protection for low-lying areas such as Kurla, LBS Marg, Teacher's Colony and the Drive-in Theatre corridor. 
The second major component focuses on tackling pollution by intercepting sewage before it enters the river. The BMC estimates that around 309 million litres of sewage currently flow into the Mithi every day. Under the project, sewage from connected nullahs and outfalls will be diverted into the municipal sewerage network and treated through the Dharavi Sewage Treatment Plant instead of being discharged directly into the river. 
The package also includes the construction of a major sewage pumping station, likely near Machhimar Colony in Mahim, along with new sewer lines, retaining walls and service roads that will improve maintenance access while strengthening vulnerable riverbanks. 
One of the biggest challenges facing the project is the rehabilitation of around 2,000 families living in affected areas across K East, L and H East wards, including parts of Dharavi and Kurla. Civic authorities have begun surveys to identify eligible residents for rehabilitation, alongside technical assessments at proposed pump locations to determine pumping capacity requirements. 
Although project documents mention December 2031 as the contractual completion date, BMC officials have stated that the civic body's operational target is to complete the works by December 2029 through simultaneous execution of rehabilitation and engineering works. 
The Kurla-Mahim package forms one of four components of the broader Mithi River rejuvenation programme, which aims to transform the river into an integrated flood-management and sewage-control corridor rather than a conventional river-cleaning exercise.