The Bombay High Court has allowed the Brihanmumbai Municipal Corporation to fell 1,237 mangrove trees across 2.7515 hectares, clearing a key hurdle for the long-pending Madh-Versova bridge. A bench led by Chief Justice Mahesh Chandra Tripathi held that the project's reduction in travel distance and time must be weighed against environmental concerns. The 2,064-metre cable-stayed bridge over Malad Creek is expected to cut the 21-km road journey between Madh and Versova to around 1.5 km, reducing travel time from nearly 90 minutes to about five minutes.
The Bombay High Court has cleared the way for the long-pending cable-stayed bridge connecting Madh Island and Versova, allowing the civic body to cut mangroves required for the project. A division bench of Chief Justice Mahesh Chandra Tripathi and Justice Advait Sethna passed the order while allowing a petition filed by the Brihanmumbai Municipal Corporation (BMC), holding that environmental and developmental requirements needed to be balanced.
The petition, registered as Writ Petition (L) No. 17795 of 2026 and filed under Article 226 of the Constitution, had sought permission to clear 1,237 mangrove trees spread across 2.7515 hectares to facilitate construction of the bridge over Malad Creek. Such permission is mandatory under a 2018 Bombay High Court judgment delivered in a public interest litigation concerning mangrove protection across Mumbai's coastal areas. Senior counsel Aspi Chinoy, appearing for the BMC along with advocate Joel Carlos, submitted that the 2,064-metre elevated bridge represented a crucial missing link in Mumbai's road network. Counsel told the court that all requisite regulatory permissions, including coastal and forest-related clearances, had already been obtained.
The Union of India, the Maharashtra Coastal Zone Management Authority and the state government were among the respondents in the matter. The Bombay Environment Action Group, an environmental body, was also implemented as a respondent and had earlier been permitted to place its objections on record during the proceedings, which had been heard over several sittings since mid-2026 before the final order was passed.
The court was informed that the BMC had deposited around Rs 1.42 crore towards compensatory mangrove afforestation over nine hectares in Thane district. A separate mangrove restoration plan worth Rs 12.50 crore was also cited, under which 2.5 hectares would be restored in situ after construction is completed. Officials noted that only about 0.20 hectares would remain permanently occupied by the bridge's piers and pylons, with the remaining area to be restored once work concludes.
The bench observed that the proposed bridge would reduce the existing 21-km road journey between Madh and Versova to approximately 1.5 km, cutting travel time from nearly 90 minutes to about five minutes. The court remarked that the reduction in travel distance was evident and that a balance needed to be struck between environmental protection and development needs.
The civic body had earlier told the court that the existing route, which requires long detours through congested roads via Link Road, S V Road or the Western Express Highway, could take up to 1.5 hours during peak periods. Residents of Madh Island currently rely on seasonal ferry services, which remain suspended for several months each year during the monsoon. The BMC maintained that the bridge would ease congestion, cut travel time and reduce vehicular pollution, claiming the project could lower carbon dioxide emissions from the corridor by more than 93 per cent once operational.
The Madh-Versova bridge was first proposed in Mumbai's 1967 Development Plan and had been held up over multiple rounds of coastal and environmental clearances. The Maharashtra Coastal Zone Management Authority had earlier asked the BMC to revise the bridge's alignment to reduce its ecological footprint, following which coastal clearance was granted in February 2023. The Union Ministry of Environment, Forest and Climate Change subsequently granted in-principle approval for the project, valued at approximately Rs 2,395 crore, after which the BMC approached the Bombay High Court seeking final clearance for mangrove felling within the coastal regulation zone. The construction contract for the project had already been awarded, with preliminary surveys and soil testing at the site having commenced in December 2025.
With the High Court's approval now in place, construction of the bridge is expected to proceed, connecting Madh Jetty Road to a point near Fisheries University Road in Versova. The project is also planned to link with the upcoming northern phase of the Mumbai Coastal Road, extending connectivity towards Dahisar and Bhayandar.
Note: This draft incorporates procedural details (petition number, respondents, BEAG's role) from the Indian Kanoon record of the case's June 18, 2026 interim hearing, alongside the Free Press Journal's September 9, 2026 report on the final order and background from earlier coverage of the project's clearances. The signed text of the final order itself is still not publicly indexed - flagging this per your sourcing standards.
Source- India Kanoon / Multiple Sources