The July rockfall on the Mumbai-Pune Expressway’s Missing Link has prompted the Maharashtra State Road Development Corporation (MSRDC) to strengthen protection on the hillside above the tunnel mouths. Boulders weighing an estimated 17–20 tonnes fell during the July 6 landslide, damaging the tunnel entrance’s false frame. Following a slope assessment by IIT Bombay, additional measures are now being implemented across about 1.38 hectares. Around 50–60% of the work is complete, with MSRDC targeting October-end for completion of the protection measures.
The Maharashtra State Road Development Corporation (MSRDC) is stepping up rockfall protection along a vulnerable hillside on the Mumbai-Pune Expressway’s Missing Link after the July landslide exposed risks beyond the portion of the slope covered by the project's original protection system.
The immediate focus is the area above the tunnel mouths, where additional stabilisation work is now under way. MSRDC said around 50–60% of the measures have been completed, with the remaining work targeted for completion by the end of October.
The intervention follows the July 6 incident, when intense rainfall triggered a rockfall near the mouth of the 8.9-km tunnel. Some of the boulders that came down were estimated to weigh between 17 and 20 tonnes. The falling material damaged the false frame at the tunnel entrance, while water that emerged through the hillside also flowed across the Mumbai-bound carriageway.
The incident did not result in reported structural damage to the main tunnel. MSRDC had said after the landslide that the damage was confined to the external entrance structure, allowing the tunnel itself to remain operational after inspections.
What the episode highlighted, however, was the exposure of higher sections of the hillside during extreme rainfall. The Missing Link already had rockfall protection extending to about 15 metres above the tunnel exits. The July event prompted the corporation to examine and strengthen areas higher up the slope.
IIT Bombay subsequently assessed the hillside and recommended additional mitigation measures. The current work is being carried out by Navayuga Engineering Company Ltd, the tunnel contractor, under MSRDC's supervision.
The protection programme is spread over approximately 1.38 hectares of hillside. One of the first interventions involves dealing with water movement. New channels formed on the slope during the heavy rainfall are being diverted so that water does not continue flowing through vulnerable portions of the rock face and contribute to further weakening.
MSRDC is also removing loose and weathered rock from identified sections. Where rock needs to be secured, steel anchors are being drilled into the hillside to connect the outer rock layer with more stable material underneath.
High-tensile steel mesh is being installed over selected portions to contain smaller loose rocks. Steel barriers are being placed at different levels to intercept larger rocks that could still detach from the slope. The measures are being applied according to the condition of individual sections rather than uniformly across the entire hillside.
The strengthened protection is also being designed against a higher weather-event benchmark. According to MSRDC, the additional sections are being designed for a 1-in-1,000-year event, compared with the original 1-in-100-year design benchmark.
The immediate priority remains the hillside directly above the July landslide location. Similar protection measures are also planned above the other tunnel mouths of the Missing Link.
The 13.3-km Missing Link was developed as an alternative to the existing Khandala ghat section of the Mumbai-Pune Expressway. The project, built at a reported cost of 6,695 crore, is intended to provide a shorter route between the Khopoli and Pune-side sections of the corridor.
For MSRDC, the present exercise is therefore not a repair of the main tunnel but an expansion and strengthening of hillside protection after the first monsoon exposed a vulnerability at higher elevations. With more than half of the additional work already completed, the corporation is working towards securing the identified stretch by October-end.