SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Elphinstone Bridge-Sewri-Worli connector unlikely to open for traffic before next year

#Infrastructure News#Infrastructure#India#Maharashtra#Mumbai City#Prabhadevi
Synopsis

The new double-decker Elphinstone Bridge in Prabhadevi and the wider Sewri-Worli Connector are unlikely to open for traffic before next year, with the project now expected to be completed in January or February 2027, well past its original September 2026 deadline. The delay has been attributed to a combination of factors, including a slower-than-expected demolition process, unexpected civic utility work, a shortage of workers and disruptions caused by the monsoon. The century-old Elphinstone Bridge was shut to traffic on 12 September 2025 to make way for the new structure.

The new double-decker Elphinstone Bridge in Prabhadevi, along with the broader Sewri-Worli Connector, is unlikely to open for traffic before next year, with the Mumbai Metropolitan Region Development Authority (MMRDA) now targeting completion in January or February 2027, missing its original September 2026 deadline. 
The delay has been attributed to a combination of factors, including a slower-than-expected demolition process for the century-old bridge, unexpected civic utility work, a shortage of construction workers, and disruptions caused by the ongoing monsoon. Officials said most of the remaining construction work is expected to be completed by December, with final works continuing into early 2027. 
The 112-year-old Elphinstone Bridge, which had linked Parel with Prabhadevi-Worli for over a century, was closed to traffic on 12 September 2025 to make way for the new double-decker structure. Following the closure, work began on demolishing the old stone bridge and dismantling its railway sections, a process that has since been completed, with the last 132-metre stretch above active Central Railway tracks brought down between Parel and Currey Road, with MahaRail deploying more than 150 workers and three heavy cranes to complete the job. 
The lower deck of the new structure will replace the existing Elphinstone Bridge, providing a 2+2 lane carriageway for traffic between Dr Babasaheb Ambedkar Road and Senapati Bapat Road, effectively restoring the connectivity currently served by the older bridge. The upper deck will form part of the broader 4.5-kilometre Sewri-Worli Elevated Corridor, carrying a separate 2+2 lane carriageway for traffic moving between Worli and the Mumbai Trans Harbour Link, also known as Atal Setu, and vice versa. 
According to officials, the railway section of the new bridge was expected to be completed by November, after which the MMRDA and its contractor, J Kumar, would begin connecting this railway section with the remaining non-railway portions of the Sewri-Worli Connector. Work on other parts of the connector has also faced separate challenges. Ahead of the monsoon, the Brihanmumbai Municipal Corporation (BMC) had written to the MMRDA raising concerns over excavation and piling work along the alignment, saying construction activity had caused siltation and damaged sewage lines in the area, and had asked the authority to remove scaffolding that was blocking footpaths. Residents in the vicinity had also complained of air pollution linked to the construction, prompting work to continue during night hours in an effort to minimise disruption. 
Once completed, the Sewri-Worli Connector is expected to significantly cut travel time between the two points, connecting the Bandra-Worli Sea Link to the Mumbai Trans Harbour Link and reducing the Sewri-Worli journey to under 10 minutes. The corridor rises approximately 27 metres above ground at points, crossing railway lines at Sewri, Parel and Prabhadevi, with the section over the Central and Western Railway lines near Prabhadevi Road station forming a double-decker structure, described by MMRDA officials as the most challenging portion of the project. MMRDA Commissioner Sanjay Mukherjee has previously said the connector is expected to add around 15 to 20 per cent additional vehicular traffic from Bandra to Worli and the Mumbai Coastal Road to Atal Setu, in turn increasing toll revenue on the Atal Setu. 
The overall Sewri-Worli Elevated Corridor project has been valued at approximately INR 1,286 crore, with the railway overbridge portion alone estimated to cost around INR 167.35 crore. 
The report did not specify a firm, final completion date beyond the January-February 2027 window cited by officials, nor did it detail whether further monsoon-related or utility-related delays could push the timeline out further.