Private power transmission developers have urged the Ministry of Power to strengthen the obligations of Central Transmission Utility of India Ltd and provide automatic financial relief to projects delayed by unavailability of interconnected transmission infrastructure. The Electric Power Transmission Association has sought changes including a deemed commercial operation date, full tariff recovery and protection from penalties where a project's commissioning is held up by delays in separately awarded interconnected facilities, warning developers face mounting costs for delays beyond their control.
Private power transmission developers have urged the Ministry of Power to strengthen the obligations of Central Transmission Utility of India Ltd and provide automatic financial and contractual relief to projects delayed by the unavailability of interconnected transmission infrastructure.
In a representation to Power Secretary Pankaj Agarwal, the Electric Power Transmission Association has sought changes to the tariff-based competitive bidding framework governing inter-state transmission projects, including a deemed commercial operation date, full tariff recovery and protection against penalties where a project's commissioning is held up by delays in separately awarded interconnected facilities. The association warned that developers are being exposed to mounting costs for delays beyond their control, as transmission projects are increasingly interdependent, with completion of a line, substation, bay or reactor developed by one provider often contingent on the readiness of an interconnected asset being developed under a separate package by another developer.
When the latter is delayed, a transmission service provider that has completed all work within its control may be unable to charge or commission its asset and begin recovering tariff, leaving it exposed to debt-servicing costs, interest during construction, operation and maintenance expenses, insurance, working-capital requirements and extension costs for bank guarantees, the association said. It argued that the existing transmission service agreement framework assigns the nodal agency a coordination role for interconnection facilities, but does not provide sufficiently specific and enforceable obligations, defined timelines or automatic commercial relief when interconnected infrastructure is delayed.
The association has asked the government to expand the utility's responsibilities to include time-bound coordination to ensure the availability of interconnected transmission elements, and to facilitate technically feasible alternative arrangements where the originally planned interconnection facility is not ready. A key demand is that transmission developers should be granted a deemed commercial operation date once they have completed all works capable of being undertaken, even if the project cannot be charged because an interconnected facility is unavailable, with provisional recovery of the full annual transmission charges from that date. The association has also sought a day-for-day extension of scheduled commercial operation dates and protection from liquidated damages and termination consequences where delays are not attributable to the affected provider.
The association said the absence of such provisions created open-ended financial exposure for developers who continue to bear project costs without corresponding tariff recovery, despite having completed their contractual obligations, and had urged the ministry to extend similar relief to projects already under implementation and affected by such delays. The representation comes as India accelerates transmission infrastructure development to support its target of 500 gigawatts of non-fossil-fuel-based installed capacity by 2030.
Source- PTI