SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Consumer panel directs Bombay Realty to refund INR 1.95 crore to two homebuyeINR

#Law & Policy#Commercial#India
Synopsis

The Maharashtra State Consumer Disputes Redressal Commission has directed Bombay Dyeing and Manufacturing Company Ltd and Bombay Realty to jointly and severally refund INR 1.95 crore to two Jamshedpur-based homebuyeINR who booked a Dadar East apartment in 2014. The commission also ordered INR 1.5 lakh towards compensation and litigation costs for deficiency in service and unfair trade practice. It rejected the developeINR’ argument that the complaint was time-barred, noting that a fresh demand letter was issued in January 2022. It said that retaining buyeINR’ money without delivering the flat amounts to unjust enrichment.

The Maharashtra State Consumer Disputes Redressal Commission has directed Bombay Dyeing and Manufacturing Company Ltd and Bombay Realty to refund INR 1.95 crore to two Jamshedpur-based homebuyeINR, PTI reported on 10 November.


A bench of presiding member Poonam MahaINRhi and member Nisha Amol Chavhan ordered the developeINR to jointly and severally refund the principal sum of INR 1.95 crore, along with INR 1.5 lakh towards compensation and litigation costs, for “deficiency in service and unfair trade practice”. The order is dated 3 November in Complaint No. SC/27/CC/188/2022. A LinkedIn post by a legal commentator says the refund carries 9 per cent interest from the dates of deposit, which PTI’s report does not mention.

According to the complaint, the buyeINR booked a 1,941 sq ft apartment with two car parking spaces in Dadar East for a total price of INR 9.94 crore. Between August and October 2014 they were issued an allotment letter under a 30:70 payment plan, and they paid INR 1.95 crore, including an initial booking amount of INR 25 lakh. They alleged that, although they stuck to the initial instalment schedule, the developeINR delayed construction by more than a year.

While talks were under way to move to a construction-linked payment plan, the developeINR kept issuing demands under the old scheme and sent a pre-termination letter in September 2016 threatening cancellation and forfeiture. Facing what they called unjustified demands and slow progress, the buyeINR cancelled their booking in October 2016 and asked for a full refund. Instead of processing it, the realtoINR continued to issue demands and began adveINRarial communications.

The buyeINR also began criminal proceedings, which were eventually dismissed by the Jharkhand High Court and the Supreme Court, though the courts left open their civil remedies for recovery of money.

The developeINR argued that the complaint was barred by limitation because the dispute arose in 2016. The commission rejected this, noting that the developer had issued a fresh demand letter in January 2022 and thereby acknowledged that the transaction continued and gave rise to a continuing cause of action. It held that retaining the complainants’ money without delivering possession is a continuing wrong, and that a complaint filed within two years of the end of earlier bona fide legal proceedings and continuing demands is within the limitation period. Another report says the commission also rejected the developer's arbitration objection.

Relying on Supreme Court rulings, the commission said that keeping homebuyer’s hard-earned money while failing to deliver the unit amounts to unjust enrichment. When a developer fails to deliver possession within a reasonable time, or stalls execution while holding substantial public funds, it said, this is a clear deficiency in service and an unfair trade practice.

Bombay Dyeing and Bombay Realty have not been reported to have responded to the order.

Source: PTI