SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

GAIL to invest INR 600 crore in Ratnagiri LNG terminal heating unit by June 2027

#Taxation & Finance News#Infrastructure#India#Maharashtra
Synopsis

GAIL India will invest INR 600 crore to build a heating unit at its Ratnagiri liquefied natural gas (LNG) terminal in Maharashtra, with completion targeted for June 2027. The facility is expected to enable the terminal to operate at its full capacity of 5 million tonnes per annum (mtpa), compared with around 50% utilisation currently. The project follows the loss of an earlier waste-heat source from a power plant operated by another entity. GAIL is also developing a small captive power plant to supply heat to the LNG facility.

GAIL India is investing INR 600 crore to construct a heating unit at its Ratnagiri liquefied natural gas (LNG) terminal in Maharashtra, a project expected to restore the facility’s ability to operate at its full capacity of 5 million tonnes per annum (mtpa). 
R. K. Singhal, GAIL’s business development director, announced the investment on October 28 at an industry event. The heating unit is scheduled for completion by June 2027 and will provide the heat required to convert super-chilled LNG into gaseous form for supply and use. 
The terminal is currently operating at approximately 50% of its capacity because the heating unit is not ready, Singhal said. The facility previously relied on waste heat from a power plant operated by another entity to gasify LNG. However, that power plant is no longer operational, leaving the terminal without its earlier heat source. 
The proposed investment is intended to address this constraint and allow the terminal to use its installed capacity more fully. The planned heating infrastructure is therefore a key requirement for improving utilisation at the facility. 
Alongside the heating unit, GAIL is building a small captive power plant to generate heat for the LNG terminal. The company has not disclosed further details about the captive plant’s capacity, project cost or commissioning schedule in the reported announcement. 
LNG is transported and stored in liquid form at very low temperatures, reducing its volume for handling and transportation. Before it can be supplied through gas infrastructure, it must be warmed and converted back into gaseous form, a process known as regasification. The availability of a dependable heat source is consequently important for maintaining terminal operations. 
The Ratnagiri project highlights the role of supporting utilities in determining the effective operating capacity of energy infrastructure. Although the terminal has an installed capacity of 5 mtpa, the absence of the required heating facility has limited its current utilisation to about half that level. 
GAIL’s planned investment is focused on restoring the infrastructure needed to support higher throughput rather than announcing an expansion beyond the terminal’s existing capacity. The June 2027 completion target will be an important milestone in determining when the facility can move towards full-capacity operations. 
The company has not provided a revised utilisation timeline beyond the stated completion target for the heating unit. 
Source: Reuters