Adani Energy Solutions expects to commission three to four transmission projects in the second half of the current financial year, adding about INR 1,300 crore to its annualised transmission tariff, chief executive Kandarp Patel told analysts. The projects are WRSR, Halvad, Khavda IV-A and Navinal Transmission. The company has 15 projects under construction with an outlay of INR 87,000 crore. It won the Satara and Vizag transmission projects during the quarter. It expects Competition Commission of India approval for the INR 3,050 crore IntelliSmart acquisition within a month.
Adani Energy Solutions Limited (AESL) expects to commission three to four transmission projects in the second half of the current financial year, adding around INR 1,300 crore to its annualised transmission tariff, chief executive officer Kandarp Patel told analysts during a post-results call. The second half of FY27 runs from October 2026 to March 2027. Annualised transmission tariff refers to the yearly payment a project is entitled to under its transmission service agreement once it is commissioned.
The projects are WRSR Transmission, Halvad Transmission, Khavda IV-A Transmission and Navinal Transmission, according to the company’s investor presentation. AESL has 15 transmission projects under construction, with a combined capital outlay of INR 87,000 crore. That works out to an average of about INR 5,800 crore per project.
During the quarter, the company won two projects: the INR 4,700-crore Satara Transmission project and the INR 8,500-crore Vizag Transmission project. The two projects won during the quarter have a combined value of INR 13,200 crore.
The company remains on track to invest INR 6,000 crore in transmission capital expenditure in the second half of FY27, over and above the INR 5,500 crore invested in the first half, Patel said. Together, the two periods add up to INR 11,500 crore of transmission capital expenditure for the year.
On the proposed acquisition of smart metering company IntelliSmart Infrastructure, Patel said AESL expects to receive approval from the Competition Commission of India (CCI) within a month. The company would then begin integrating the business into its operations. The company announced the acquisition of IntelliSmart Infrastructure for INR 3,050 crore in June.
Management had said on the earlier call for the April-June quarter, held in July, that the acquisition was pending CCI approval and that the company would formally take over the entity only after all approvals are in place. Combined with AESL’s existing smart-meter base, the portfolio would total about 47 million meters, management said on that call. Management also said then that it expects annual capital expenditure additions of roughly INR 20,000 crore to INR 25,000 crore, based on the company retaining about a 25 per cent market share. The company cited a network of about 28,000 circuit kilometres of transmission lines on that call. On that call, management said capital expenditure in the first quarter was close to INR 3,500 crore.
Management also said its KPS HVDC project is expected to be commissioned in FY29, around December 2029, and that a project in Rajasthan is expected at the beginning of 2029. Management said the Mumbai HVDC link was commissioned in the previous year and helped the region during the summer. It expects IntelliSmart’s return profile and profitability to be broadly similar to AESL’s existing smart-metering business. Management added that right-of-way challenges exist on the ground and are worked on in parallel with state processes. The investor presentation listed the four named projects as the ones scheduled for commissioning.
Source- Adani Energy Solutions
17th Nov, 2026
17th Nov, 2026