EKA Mobility is aligning its electric bus production with the availability of depot and charging infrastructure, as delays in power connections and site preparation hold up vehicle deliveries. The Pune-based manufacturer estimates it can deliver around 2,000 buses over the next two years from an order book of approximately 11,000. Chairman Sudhir Mehta said depot readiness typically takes about a year after an order is placed. The company is therefore adjusting manufacturing schedules to avoid accumulating buses that cannot yet be deployed.
EKA Mobility is scaling its electric bus production in line with the readiness of charging infrastructure, as delays in preparing depots and securing electricity connections continue to affect deliveries. The Pune-based electric vehicle manufacturer can deliver around 2,000 buses over the next two years from an order book of approximately 11,000, chairman Sudhir Mehta told The Economic Times.
Mehta said production capacity was not the principal constraint on deployment. Instead, the time required to establish depot infrastructure, including land handover, electricity connections, charging equipment and transmission capacity, was delaying the movement of completed buses to operating locations. Depot infrastructure typically takes about a year to become ready after an order is placed.
The company has consequently changed its production planning to correspond with the expected availability of depots. Mehta said EKA had previously accumulated buses at its factory that could not be dispatched because the necessary infrastructure was incomplete. The manufacturer is now monitoring depot readiness before scheduling production.
The issue also involves the financing and procurement arrangements for electric bus projects. Under the existing model, the original equipment manufacturer supplies and services the buses, while an operating partner is responsible for financing, charging facilities, electricity connections, depot development and drivers. State transport undertakings may take six to eight months to issue a letter of award after a tender, adding to the time before deployment can begin.
Mehta said banks also seek assurance that charging infrastructure is available before financing the buses. This can create a cycle in which operators cannot secure vehicle financing without depot readiness, while manufacturers cannot dispatch buses without payment. He has called for governments to tender depot and charging infrastructure separately and ahead of bus procurement, with transport authorities mapping requirements over five to 10 years.
In an earlier interview with Business Standard in September, Mehta said infrastructure preparation could take 12 to 24 months, while bus deployment could be completed within a few months once facilities were ready. At that time, EKA reported an order book of around 10,500 buses, with more than 1,500 delivered and approximately 9,000 remaining for delivery over 18 to 24 months.
The company has also been expanding manufacturing capacity. EKA Mobility and group company Pinnacle Industries inaugurated six facilities in Pune and Madhya Pradesh in October, taking their network to 11 plants with annual capacity to manufacture more than 40,000 electric vehicles across categories. The group has outlined a INR 2,000 crore capital expenditure plan over three years.
EKA's deliveries are spread across more than 40 cities. The company is completing a 750-bus order for Rajasthan and has begun operations in Andhra Pradesh and Bihar. Mehta has also identified electric trucks as a future growth area, with trials completed with more than 50 customers.
The production adjustment reflects the need to coordinate vehicle manufacturing with the infrastructure required to put electric buses into service. EKA's delivery pace will therefore depend not only on its manufacturing capacity and order pipeline but also on the readiness of depots, power supply and charging facilities.