SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Telangana RERA restrains sale and transfer of nine flats in Tellapur project amid double-sale allegations

#Law & Policy#Commercial#India#Telangana
Synopsis

The Telangana Real Estate Regulatory Authority (TGRERA) has restrained the developer of Tripuras Green Alpha, a residential project in Tellapur, from selling, mortgaging or creating third-party rights over nine flats following complaints from homebuyers. The interim order, dated October 29, 2026, covers seven apartments in Block A and two in Block E. The buyers alleged that they had paid the full or a substantial portion of the agreed consideration but had not received registered sale deeds. The authority said their concerns warranted protection while the complaints are being heard.

The Telangana Real Estate Regulatory Authority (TGRERA) has barred the developer of Tripuras Green Alpha from undertaking further transactions involving nine residential units at its Tellapur project in Sangareddy district, following complaints of alleged double sales and delays in executing sale deeds. 
In its common interim order dated October 29, the authority directed the developer, its partners, agents and anyone acting on its behalf not to sell, mortgage, transfer or create third-party rights over the specified apartments until further orders. The restraint covers seven flats in Block A - numbers 411, 1006, 608, 502, 811, 210 and 503 - and two flats in Block E, numbers 404 and 906. 
The complaints were filed by nine homebuyers who claimed to have paid the entire or a substantial portion of the agreed sale consideration for their respective apartments. They alleged that although the developer had acknowledged receiving the payments, it had failed to execute the sale deeds despite delays extending beyond the committed completion timeline. 
The buyers further alleged that the developer had demanded additional amounts and threatened to cancel their existing allotments and sell the apartments to other purchasers. Their concerns were heightened by allegations of double sales involving other units in the same project. 
During the proceedings, the developer's counsel did not deny the earlier allegations of double sales but submitted that alternative apartments would be allotted to the affected buyers. The authority, however, considered the apprehensions raised by the nine complainants genuine and said the possibility of further transactions needed to be addressed. 
TGRERA observed that allowing the developer to sell or transfer the disputed apartments could lead to additional litigation and potentially make any eventual orders ineffective. After considering the claims of payment and allotment, it found a prima facie case in favour of granting interim protection and held that the balance of convenience supported the complainants. 
The authority invoked Section 36 of the Real Estate (Regulation and Development) Act, 2016, to impose the restrictions. It also warned that any violation of the directions could invite action under Section 63 of the Act. 
The latest order follows similar interim relief granted by TGRERA on July 21, 2026, in other complaints concerning the same project. The regulator has therefore intervened more than once to prevent further transactions involving apartments under dispute. 
However, the October 29 order does not amount to a final decision on the allegations or establish ownership rights in favour of the complainants. It also does not award refunds or compensation. The complaints remain subject to further proceedings before the authority, which will determine the parties' claims and the developer's obligations. 
Source- Telangana RERA