SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Telangana HC quashes 2006 acquisition of 92.39 acres in Tellapur, relief for plot owners

#Law & Policy#Land#India#Telangana
Synopsis

The Telangana High Court has quashed the 2006 acquisition notification and 2007 declaration for 92.39 acres in Tellapur, near Hyderabad, intended for a township, as far as they relate to the petitioners' lands. Justice Vakiti Ramakrishna Reddy found that the notification did not clearly state the purpose of acquisition, that the objection inquiry had been reduced to an empty formality and that compliance with the Andhra Pradesh Urban Areas (Development) Act, 1975 was not shown. The authorities may initiate fresh acquisition in accordance with law.

The Telangana High Court has quashed the acquisition proceedings initiated in 2006 for 92.39 acres of land in Tellapur for the formation of a township, holding that the proceedings suffered from serious procedural and substantive illegality. 
Justice Vakiti Ramakrishna Reddy allowed a batch of six writ petitions filed by the Tellapur 'G' Block Plot Owners' Association and five other private persons, challenging the acquisition initiated by the district collector of Medak in 2006 and the declaration issued in 2007 under the Land Acquisition Act. The court granted liberty to the authorities to initiate fresh acquisition proceedings in accordance with law. 
The petitioners had bought plots in Block 'G' of a layout developed by the Industrial Employees Co-operative House Building Society. The society had acquired a larger extent of land, obtained layout approval in 1976 and allotted plots to its members through registered sale deeds. 
The petitioners argued that Block 'G', which has 594 plots, consists of patta land and had been excluded from a proposed acquisition following a government decision in 1989. They also pointed out that the layout regularisation process has remained pending, which has prevented plot owners from obtaining building permissions. 
Under the Land Acquisition Act, 1894, a notification under Section 4(1) signals that land is likely to be needed for a public purpose, owners can object under Section 5-A, and a later declaration confirms the decision to acquire. The 1894 Act was replaced by the 2013 land acquisition law with effect from 1 January 2014. 
The court found that the notification issued under Section 4(1) of the Land Acquisition Act failed to specify the purpose of acquisition with the required clarity. It held that the inquiry under Section 5-A, which gives landowners an opportunity to raise objections, had been reduced to an empty formality, as their objections were rejected without adequate reasons or proper application of mind. 
The court also observed that the authorities had failed to establish compliance with Section 18 of the Andhra Pradesh Urban Areas (Development) Act, 1975, which required the government to form an opinion that the land was needed for development. It quashed the acquisition notification dated 22 February 2006 and the declaration dated 3 February 2007 insofar as they related to the petitioners' lands. 
Telugu reports said the land is in Ramachandrapuram mandal, now part of Sangareddy district, and that the acquisition notification, issued by the then Hyderabad Urban Development Authority (HUDA), described the purpose only as setting up a township and developing future projects, which the judge found vague. 
As the quashing applies only insofar as the notification and declaration relate to the petitioners' lands, the position of other landowners within the 92.39 acres is not clear from the reports. 
For plot owners in Block 'G', the ruling lifts the acquisition cloud over their plots, though layout regularisation remains a separate process.