SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Lucknow Development Authority plans completion charge to fund pending works in Sushant Golf City

#Law & Policy#Infrastructure#India#Uttar Pradesh#Lucknow
Lucknow News Desk Last Updated : 24 Oct 2026
Synopsis

The Lucknow Development Authority is planning a township completion charge to help fund pending infrastructure works in the stalled Ansal API township in Sushant Golf City. The charge, proposed at around INR 1,150 per sq m, would apply at the time of new map approvals, compounding or completion. The move follows the Uttar Pradesh Cabinet’s approval of the authority’s takeover proposal, with remaining works estimated at over INR 2,200 crore. Execution awaits clearance from the National Company Law Tribunal, where the next hearing is due in November.

The Lucknow Development Authority (LDA) is planning to levy a township completion charge on property owners in Sushant Golf City to help fund pending development works in the stalled Ansal API township, as it moves ahead with taking over the project. 
Under the proposal, the charge would be levied at the time of approval of new building maps, compounding of maps or completion. Based on a preliminary assessment, the charge has been proposed at around INR 1,150 per sq m. 
The proposal follows the Uttar Pradesh Cabinet’s approval on September 15 of the LDA’s plan to take over the township and complete its pending infrastructure. Ansal Properties and Infrastructure Limited, the developer, is undergoing corporate insolvency resolution proceedings. 
LDA Vice-Chairman Prathamesh Kumar said the charge was being considered because a large portion of the land mortgaged with the authority as security had already been sold by the private developer. This has left the LDA with limited scope to raise funds by using the mortgaged plots. 
Under the High-Tech Township Policy, the developer had mortgaged plots with the LDA as a performance guarantee. The state Cabinet has since cleared the LDA’s proposal to release 2,747 mortgaged plots through a structured process instead of cancelling their registries, allowing development work to proceed. 
The estimated cost of the remaining infrastructure works in the township is around INR 2,216.91 crore. This includes INR 453.10 crore for works in pockets one to four and INR 1,126.52 crore for pocket five. The pending railway overbridge has been estimated at INR 114.28 crore, while INR 523 crore has been earmarked for electricity substations. 
Pending works include roads, sewage treatment plants, sewer lines, drainage, drinking water pipelines, tube wells, substations and parks. Some of these works may require additional land acquisition. 
The LDA is also preparing a land pooling option to address cases involving around 800 large plots that were allegedly sold by the developer’s consortium members contrary to rules. Under the proposal, owners of such plots may be offered land in exchange before any cancellation of registries is considered. 
Kumar has said that the authority will act on buyers’ claims filed before the National Company Law Tribunal (NCLT) and approved by it. Buyers whose claims are approved would be considered for allotment of the corresponding property. 
The LDA’s revival plan, however, can be implemented only after it receives approval from the NCLT to develop the township. The next hearing in the matter is scheduled for November, after an earlier hearing could not take place. 
Sushant Golf City, located along Shaheed Path and the Lucknow-Sultanpur Road, is one of the largest private townships in the state capital. Around 5,000 buyers of homes and shops in the township have been awaiting completion of basic infrastructure for several years. 
The completion charge, if approved, would apply in addition to the funds the LDA expects to raise from the remaining available land within the township.