SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Western Railway builds INR 307 crore Sabarmati hub for Vande Bharat maintenance

#Infrastructure News#Infrastructure#India
Synopsis

Western Railway is developing an INR 307 crore maintenance hub at Sabarmati in Ahmedabad to carry out scheduled maintenance of Vande Bharat trains, with the heavy repair bay shed nearing completion and the wheel care shed already built. The facility, part of Phase II of the Sabarmati Integrated Coaching Depot, will handle SS-I and SS-II maintenance of 24-coach trainsets, with annual capacity of about 12 rakes for SS-I or eight for SS-II, according to IANS. It will reduce the need to send trainsets to other locations for major maintenance.

The Western Railway is developing an INR 307 crore maintenance hub at Sabarmati in Ahmedabad to carry out scheduled maintenance of Vande Bharat trains, with construction of the heavy repair bay shed nearing completion and the wheel care shed already built, according to IANS. 
The project is being undertaken by the Ahmedabad Division as Phase II of the Integrated Coaching Depot (ICD) at Sabarmati. It is designed to reduce the need to send trainsets to other locations for major maintenance. The facility will handle scheduled soft schedule maintenance, known as SS-I and SS-II, of 24-coach Vande Bharat trainsets. SS-I maintenance of a 24-coach rake can be completed in around 30 days, while SS-II is expected to take about 45 days. 
The depot is designed to undertake SS-I maintenance of about 12 rakes or SS-II maintenance of eight rakes a year. The project includes a heavy repair bay shed, section sheds, a wheel care shed, a tandem wheel lathe shed, a drop pit, retractable overhead equipment, machinery and plant, and other associated facilities. 
The heavy repair bay shed, measuring 322 metres by 25 metres and covering 86,597 sq ft, is almost complete. It will have two maintenance lines: one with synchronised pit jacks to lift coaches and remove bogies, and the other to maintain coach interiors, passenger amenities, braking systems and electrical equipment. 
The section sheds, measuring 322 metres by 20 metres and covering 69,334 sq ft, are being developed for dismantling, assembly and overhauling of major mechanical and electrical equipment, including traction transformers, traction converters, traction motors, auxiliary converters, isolation transformers, pantographs and roof-mounted package units. 
The wheel care shed, measuring 75 metres by 40 metres and covering 32,292 sq ft, has been completed, and the shed and its service building are ready for handover. It will handle wheel and axle overhauling, resurfacing and turning, with a CNC surface wheel lathe, a CNC axle turning lathe, a dynamic wheel balancing machine and a hydraulic wheel press. 
Rail linking has been completed across about 2,547 metres of four stabling lines, and work on both maintenance lines in the heavy repair bay shed is nearly complete. A 30 metre by 20 metre electrical sub-station building covering 6,458 sq ft has been completed and handed over. 
The reports did not specify a commissioning date or a construction timeline. 
It will allow several major repair activities to take place at a single location, according to Business World. On 4 October, Western Railway said it had installed a 620 metre Retractable Rigid Overhead Conductor System at the Sabarmati Integrated Coaching Depot, the first in the zone, letting Vande Bharat trains move directly to the depot under electric power without a diesel shunting engine. 
In 2023, a contract for the Sabarmati depot was reported at INR 241.75 crore, according to Swarajya. Western Railway also began Surat-Udaipur Vande Bharat services on 3 and 4 October, according to its release.