SBI Term Loan: RLLR: 8.15 | 7.25% - 8.55%
Canara Bank: RLLR: 8 | 7.15% - 9.85%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.35% - 10.75%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 7.35% - 9.6%
IndusInd Bank: RLLR: -- | 7.6% - 10%
Bank of Maharashtra: RLLR: 8.05 | 7% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%
HDFC Bank: RLLR: -- | 7.75% - 13.2%
Axis Bank: RLLR: -- | 8% - 9.1%
IDBI Bank: RLLR: -- | 7.4% - 10%

Delhi High Court stays NHAI debarment orders against PNC Infratech and Awadh Expressway

#Law & Policy#Infrastructure#India#Delhi
Synopsis

The Delhi High Court has stayed the debarment orders issued by the National Highways Authority of India (NHAI) against PNC Infratech and its subsidiary, Awadh Expressway Pvt Ltd, providing interim relief to the infrastructure developer. The orders, dated September 11 and September 3, 2026, respectively, had restricted the entities from participating in relevant highway project bids for three years. PNC Infratech said it was evaluating legal remedies in the matter. The company also stated that its development, construction, operations and maintenance activities would continue without disruption while the legal proceedings progress.

The Delhi High Court has granted interim relief to PNC Infratech Ltd and its subsidiary Awadh Expressway Pvt Ltd by staying the debarment orders issued by NHAI against the two entities. The court passed its order on October 12, 2026, temporarily halting the effect of the restrictions imposed by the highways authority. The debarment order against Awadh Expressway was issued on September 3, 2026, while the order extending the action to PNC Infratech was dated September 11, 2026. According to the company’s regulatory disclosure, NHAI had extended the debarment imposed on Awadh Expressway to PNC Infratech because it is the promoter of the concessionaire. The company obtained a copy of the court order from the Delhi High Court’s website on October 13. 
The three-year debarment had restricted the company and the concessionaire from participating in bids for projects tendered by NHAI, the Ministry of Road Transport and Highways and their executing agencies. The court’s interim order provides temporary relief from the effect of these restrictions while the matter remains subject to further legal proceedings. PNC Infratech has said that development, construction, operations and maintenance activities undertaken by the company and its subsidiaries will continue without disruption. The clarification indicates that ongoing project execution is expected to remain unaffected by the latest development. The company has also stated that it will disclose any financial implications arising from the matter, if applicable, as further clarity emerges. 
The company had previously disclosed developments relating to the debarment in August and September 2026. Following the latest court order, it is evaluating its legal options in connection with the action taken by NHAI. The interim relief does not, by itself, amount to a final resolution of the dispute, and the subsequent legal process will determine how the matter progresses. For PNC Infratech, the outcome is relevant to its ability to pursue future highway contracts under the concerned authorities, in addition to maintaining its existing project operations. The temporary stay changes the immediate position created by the debarment orders, although the final implications will depend on further developments in the case. The company has not quantified any potential financial impact from the proceedings. 
The development places the focus on the next steps in the legal process and any further directions issued by the court. Until then, PNC Infratech and Awadh Expressway have received interim relief from the debarment orders, while the company continues its infrastructure development and project-related activities. 
Source PTI

Discussion