The Lucknow Development Authority (LDA) has earmarked INR 100.7 crore for roads, sewerage, drinking water and drainage infrastructure in villages covered under its IT City project. During an inspection, vice-chairperson Prathamesh Kumar found delays in road development and directed officials to accelerate work, setting a one-month deadline for improvements and restoration of roads dug up for stormwater drainage. The project covers seven villages and 10 hamlets, where 1,465 farmers have received allotments of 2,197 developed plots under the land-pooling policy.
The Lucknow Development Authority (LDA) has earmarked INR 100.7 crore for infrastructure development in villages covered under its IT City project, with the funding intended for roads, sewerage, drinking water supply and drainage systems.
The allocation was reviewed during an inspection by LDA vice-chairperson Prathamesh Kumar on Tuesday. He directed officials to expedite construction and set a one-month deadline to improve progress and restore roads dug up for stormwater drainage work.
The IT City project covers seven villages and 10 hamlets. Under the land-pooling policy, 1,465 farmers have so far been allotted 2,197 developed plots. The infrastructure works are intended to support development in the project area, where landowners are receiving developed plots in exchange for land contributed to the scheme.
During the inspection, Kumar found that construction was progressing slowly. Only three roads had reached the granular sub-base stage, despite 40 tenders having been issued for work on 25 roads and development activities in two sectors. The granular sub-base is a preparatory layer in road construction that provides a foundation for subsequent pavement layers.
The vice-chairperson directed officials to accelerate work, particularly in sectors where developed plots have already been allotted to farmers. Sectors 9, 15, 16, 17, 18 and 30 were identified for priority attention, with the authority seeking to address delays in infrastructure delivery.
The inspection also led to administrative action against officials and a consultant over the pace of implementation. Adverse entries were issued against assistant engineers Vineet Sharma, Gaurav Singh and Urvashi Srivastava. The services of outsourced revenue inspector Surya Prakash were terminated with immediate effect.
In addition, the LDA imposed a penalty of INR 1,000 per acre on architectural firm ANB for delays in submitting designs, drawings and estimates. The actions followed the review of construction progress and compliance with project timelines.
The authority’s one-month deadline covers efforts to improve the pace of infrastructure works and restore roads affected by drainage construction. The directive places the focus on completing essential services in areas where farmers have already received developed plots.
The INR 100.7 crore allocation forms part of the wider development of the IT City project, which combines land pooling with planned infrastructure and sector development. Timely completion of roads, drainage, sewerage and water supply will be important for making the allotted plots accessible and supporting further development across the project area.